| 21-Oct-2026 |
Sh. Ashish Kush, Planning Executive and Sh. Ashish Dubey, Chartered
Accountant briefed about the facts of the case.
Sh. Manoj Shukla (AR), Sh. Sunil Shekhawat (AR) and Sh. Lovekush Sharma
(AR) are present on behalf of the promoter.
The AR of the promoter company submits that an application dated 21.09.2026
has been submitted in the Authority seeking registration of the project namely
“SS Quadro” as Phase IV. The
license no. 102 of 2025 dated 17.06.2025 valid up to 16.06.2030 was issued by
DTCP in favour of M/s Growmore Buildtech Pvt. Ltd and M/s A
& D Estates Pvt. Ltd. in collaboration with the M/s A & D Estates Pvt.
Ltd. for the development of Group Housing Colony over an area admeasuring 2.55
acres in addition to the earlier license no. 195 of 2008 dated
22.11.2008 and 15 of 2023 dated 30.01.2023 which were issued in favour of M/s
Growmore Buildtech Pvt. Ltd. and Others in collaboration with M/s A & D
Estates Pvt. Ltd. for the development of Group housing colony over an area
admeasuring 12.6118 acres situated in Sector 83, Gurugram. Now, total licensed area
is 15.16175 acres.
Further, the AR of the promoter company states that the reply to the
above deficiencies has been submitted on 19.10.2026 and two third consent of the existing allottees is not required as per clause
3.1.2, (ii) of the DTCP Policy issued vide Memo no.
Misc-862/2023/7/1/2023-2TCP/11689-91 dated 24.04.2023. Clause 3.1.2 (ii) is
reiterated below.
3.1.2. However, additions or alterations in the
layout/ building plan made on account of the following shall not be construed
as revision of layout/ building plan, where:
i.
….
ii.
the existing layout/
building plan of the colony is getting amended on account of grant of license
for additional area with changes limited to an area not exceeding five percent
but not exceed 1 acres, without disturbing the green areas, of the amended combined
layout plan to enable proper connectivity and proper planning;
The Authority has considered the submissions made by the AR of the
promoter company and notes that the claim of exemption from obtaining the
consent of two-thirds of the existing allottees under Clause 3.1.2(ii) of the
DTCP Policy dated 24.04.2023 has been examined by the concerned planning
executive. Accordingly on the basis of the submissions made by the AR and
examination by the office, the exemption from obtaining the consent of
two-thirds of the existing allottees is accepted.
The AR of the promoter company further submits that presently, Revised Fire
Scheme Approval, Revised Service plan and Estimates and Revised Electrification
plan have not yet been obtained as on date. Further, the AR of the promoter
company undertakes to obtain and submit:
i.
Revised Fire Scheme within 6 months from the date of
grant of registration Certificate.
ii. Revised
Service Plans and Estimates within 6 months from the date of grant of
registration Certificate.
iii. Revised
Electrification plan within 6 months from the date of grant of registration
Certificate.
iv. Mining
permission before start of construction of project.
Further, he undertakes to submit two separate Demand Drafts/Bank
Guarantees amounting to Rs. 25 lakhs each as a security deposit for timely
compliance with the above requirement at point (i) and (ii). It is also
expressly undertaken that in the event of failure to obtain and submit the
aforesaid approvals within the stipulated time frames, the security amount
shall be liable to be forfeited by the Authority.
The Authority has taken note of the submissions made by the AR of the
promoter company regarding the non-availability of the aforesaid statutory
approvals as on date. In view of the submissions made by the AR of the Promoter,
and in the interest of regulatory compliance, the Authority hereby directs that
the promoter shall submit two separate Demand Drafts/Bank Guarantees, amounting
to Rs. 25,00,000/- (Rupees Twenty-Five Lakhs only) each, in favour of the
Authority, as security amount for timely submission of the following approvals:
a.
Revised Fire Scheme: within 6 months from the date
of grant of registration Certificate.
b.
Revised Service Plans and Estimates: within 6 months
from the date of grant of registration Certificate.
Needless to mention that in the event of non-submission of any of the
above approvals within the stipulated time frames as requested by the promoter,
the security amount shall stand forfeited by the Authority, and such failure
may also attract additional regulatory action as permissible under the Act of
2016, rules and regulations made thereunder. Further, the promoter shall submit
Mining permission before the start of construction of project and Revised
Electrification plan within 6 months from the date of grant of registration
Certificate. The conditions to the above effect be incorporated in the
registration certificate.
The promoter is further directed to apply for the amendment of
registration no. 77 of 2023 dated 17.07.2023 due to revision in the EWS block
which was already registered in the aforesaid registration certificate.
Approved as proposed subject to rectification of deficiencies mentioned
above at S. No 32 and scrutiny of the reply dated 19.10.2026.
The registration Certificate shall be issued after submission of
remaining deficiencies mentioned at S. No. 32 including correction in A-H form,
Online DPI and submission of two BG’s/DD’s of Rs. 25 lakhs each for submission
of Revised Fire Scheme approval and Revised Service plan and Estimates within
the timeframe mentioned above. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |