| 02-Nov-2026 |
Ms. Deepika, Planning
Executive and Ms. Asha, Chartered Accountant briefed about the facts of the
case.
Sh. Amarjeet Dhillon
(Director), Sh. Pankaj Hans (Director), Sh. Vikas Dua (AR) & Sh. Vikrant
Kumar (AR) are present on behalf of the promoter.
The Director of the promoter
company states that as per the latest quarterly progress report, the project is
only 14.85% complete. The Director further submits that an additional license has
been obtained by the promoter, which necessitates revisions to the building
plans. Additionally, the implementation of GRAP restrictions and shortage of labor
are cited as the primary reasons for the delay in completion of the project.
The Director of the promoter
company further submits that the requisite statutory approvals for the project,
including Revised Environmental Clearance, Revised Service Plans and Estimates,
and Revised Electrification Plan, are presently under process. With regard to
the Revised Environmental Clearance, it is submitted that the Terms of
Reference have already been granted by the Committee and the EIA report has
been uploaded, while the final approval is awaited. The promoter assures that
the Revised Environmental Clearance shall be submitted within 3 months. It is
further submitted that the Revised Service Plans and Estimates are under
approval with HSVP, and the demand for BG is expected to be raised and the
approval will be submitted within 3 months. Further, the approval of the
Revised Electrification Plan is also expected to be issued by DHBVN and will be
submitted within 3 months from extension certificate.
The Director of the promoter
company undertakes to obtain and submit the Revised Environmental Clearance,
Revised Service Plans and Estimates, and Revised Electrification Plan within a
period of three months from the date of grant of extension, as the aforesaid
approvals are presently under process.
The Director of the promoter
company further submits that, as on the date of hearing, no loan has been
availed either against the project or by the company from any financial
institution. However, to expedite the construction and completion of the project,
the promoter company is in the process of availing construction finance. In
this regard, an in-principle sanction has been issued by LIC Housing Finance
Limited (LIC HFL), subject to the grant of extension of the registration of the
project, pursuant to which the disbursement process is to commence. The
promoter company further submits that it is also exploring construction finance
from a couple of other banks to secure more favorable terms and conditions than
those offered by LIC HFL.
The Authority, after
considering the submissions made by the promoter, takes note of the fact that
the Revised Environmental Clearance, Revised Service Plans and Estimates, and
Revised Electrification Plan have not yet been obtained as on the date of hearing.
The Authority further takes note of the submission of the promoter that the
aforesaid approvals are under process and that the promoter seeks a period of
three months to obtain and submit the same. Accordingly, an undertaking shall
be furnished by the Director of the promoter company to obtain and submit all
the aforesaid approvals within three months from the date of grant of
extension. The said conditions shall also be incorporated in the Extension
Certificate, and the promoter shall ensure strict compliance with the same.
Further, with regard to the
construction finance, the Authority takes note of the submission of the
Director of the promoter company that the company is in the process of availing
a loan for expediting the construction and completion of the project and that
an in-principle sanction has already been issued by LIC HFL, subject to the
grant of extension. The Director further undertakes that, upon availing any
loan from any financial institution against the project or by the company, the
promoter shall duly intimate the Authority and furnish all relevant
loan-related documents. The Director also undertakes to submit a duly stamped
and signed affidavit in this regard before the issuance of the Extension
Certificate under Section 6 of the Act, 2016.
Approved as proposed,
subject to rectification of the deficiencies mentioned above.
The Extension of the
Registration Certificate shall be issued after the rectification of the
remaining deficiency at S. No. 46, including the submission of online DPI under
Section 6. |
EXTENSION APPROVED |
View Order |