| 21-Sep-2026 |
Sh. Sumeet, Engineering Officer and Sh. Ashish Dubey, Chartered
Accountant briefed about the facts of the project.
Sh. Shyamrup Roy Choudhary and Sh. Yatin Dev, AR are present on behalf
of the promoter.
The Authorized Representative of the promoter states that the
construction works for completion of the project are in full swing and as on
date structure work of all residential towers is completed except one tower and
water tanks on terraces of all towers. Further, the finishing works are also
progressing on the site. The AR of the promoter requests to grant an extension
of registration of project for one year under Section 6 of the Act, 2016 for
completion of the pending works in the project and to issue the extension
certificate after adding extension of four months granted by the Authority vide
order dated 11.08.2026.
In view of the above, approved as proposed subject to submission of
remaining deficiencies mentioned above as Remarks at S. No. 44. The Authority
noted that the promoter is entitled to the benefit of additional period of four
(4) months in view of the Office Order dated 11.08.2026, accordingly, the
benefit of the said 4 months period be incorporated in the certificate.
The extension of registration certificate shall be issued after
submission of documents mentioned at S. No. 44. |
EXTENSION APPROVED |