| 07-Sep-2026 |
Ms. Nikita Mittal, Planning
Executive and Ms. Asha, Chartered Accountant briefed about the facts of the
project.
Sh. Navneet Kumar (V.P.) and
Sh. Ravi Kant Kumar (AR) are present on behalf of promoter.
The Authorized Representative
(A.R.) of the promoter company submits that the promoter has applied for
registration of Phase-2, admeasuring 1.165 acres, and Phase-3, admeasuring
3.163 acres, comprising a total area of 4.328 acres, under Section 4 of the Real
Estate (Regulation and Development) Act, 2016. It is submitted that the said
phases comprise a Clubhouse and recreational area, which are non-saleable
components of the project.
The AR of the Promoter
further submits that the Fire Scheme Approval and the approved Service Plans
and Estimates in respect of the applied phases are presently under process with
the competent authorities and have not yet been obtained. The AR of the
Promoter undertakes to obtain and submit the Fire Scheme Approval within a
period of 15 days. With regard to the approved Service Plans and Estimates, it
is submitted that the requisite Bank Guarantee as required to be furnished
before DTCP, Chandigarh, shall be duly furnished, and a copy thereof shall be
submitted before the Authority within a period of 15 days and prior to issuance
of the Registration Certificate.
The AR of the promoter
further submits that, in the event the aforesaid approvals are not submitted within
15 days from today and prior to issuance of the Registration Certificate, the
AR of the promoter undertakes to obtain and submit Fire Scheme Approval as well
as Approved Service Plans and Estimates within four months from the date of
grant of Registration for which two separate Demand Drafts/Bank Guarantees
amounting to ₹25,00,000/- (Rupees Twenty-Five Lakhs only) each in favour of the
Authority, as security deposit towards submission of the Fire Scheme Approval
and approved Service Plans and Estimates, shall be furnished before the
Authority.
The Authority has taken note
of the submissions and undertakings made by the A.R. regarding the pending
statutory approvals. In the event of failure to submit the aforesaid approvals
within the prescribed time period, the corresponding security amount shall be
liable to be forfeited by the Authority, without prejudice to any further
regulatory action that may be taken under the provisions of the Real Estate
(Regulation and Development) Act, 2016, and the rules and regulations made
thereunder.
Approved as proposed, subject
to rectification/compliance of the deficiencies mentioned at S. No. 33.
The Registration Certificate
shall be issued after submission of the requisite corrections in the A-H Form,
Online DPI, fire scheme approval, approved service plans and estimates along
with compliance of the remaining deficiencies as mentioned at S. No. 33.
|
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |