| 12-Oct-2026 |
Sh. Ashish Kush, Planning Executive and Sh. Ashish Dubey, Chartered
Accountant briefed about the facts of the case.
Sh. Yogesh Kumar Sachdeva (Director), Sh. Vishwa Raman Sachdeva
(Director) and Sh. Krishan Kumar (AR) are present on behalf of the promoter.
The Director of the promoter company submits that an application dated 05.08.2026
has been submitted in the Authority seeking registration of the project namely
“Ramson Soham”. The license no. 122 of 2024 dated 14.08.2024 valid up to 13.08.2029
was issued by DTCP in favour of M/s A & I Buildcon Pvt.
Ltd. for the development of Group Housing Colony under Retirement Housing
Policy over an area admeasuring 2.775 acres.
The Director of the promoter company further submits that presently, Environment
Clearance, Fire Scheme Approval, Service plan and Estimates, Natural
Conservation Zone, Road access permission and Approval/NOC regarding Shifting
of powerline have not yet been obtained as on date. Further, the director of
the promoter company undertakes to obtain and submit:
i.
Approved Environment Clearance within 6 months from
the date of grant of registration Certificate.
ii. Approved
Fire Scheme within 6 months from the date of grant of registration Certificate.
iii. Approved
Service Plans and Estimates within 6 months from the date of grant of
registration Certificate.
iv. Road
access permission within 6 months from the date of grant of registration
Certificate.
v.
Approval/NOC regarding Shifting of powerline.
vi. NOC for
Natural Conservation Zone.
Further, he undertakes to submit three separate Demand Drafts/Bank
Guarantees amounting to Rs. 25 lakhs each as a security deposit for timely
compliance with the above requirement at point (i), (ii) and (iii). It is also
expressly undertaken that in the event of failure to obtain and submit the
aforesaid approvals within the stipulated time frames, the security amount
shall be liable to be forfeited by the Authority.
The Authority has taken note of the submissions made by the Director of
the promoter company regarding the non-availability of the aforesaid statutory
approvals as on date. In view of the above, and in the interest of regulatory
compliance, the Authority hereby directs that the promoter shall submit three separate
Demand Drafts/Bank Guarantees, amounting to Rs. 25,00,000/- (Rupees Twenty-Five
Lakhs only) each, in favour of the Authority, as security amount for timely
submission of the following approvals:
a.
Approved Environment Clearance: within 6 months from
the date of grant of registration Certificate.
b.
Approved Fire Scheme: within 6 months from the date
of grant of registration Certificate.
c.
Approved Service Plans and Estimates: within 6
months from the date of grant of registration Certificate.
In the event of non-submission of any of the above approvals within the
prescribed time frames, the security amount shall stand forfeited by the
Authority, and such failure may also attract additional regulatory action as
permissible under the Act of 2016, rules and regulations made thereunder.
The director of the promoter company is further directed to submit the road
access permission within the aforesaid stipulated timeline, NOC for Natural
Conservation Zone, and Approval/NOC for Powerline Shifting. The conditions to
the said effect shall be incorporated in the Registration Certificate.
The promoter is further directed to prominently disclose the non-receipt
of NOC for Natural Conservation Zone in the advertisement/brochure of the
project and also submit the updated copy of Brochure in view of the foregoing.
Approved as proposed subject to rectification of deficiencies mentioned
above at S. No 32.
The registration Certificate shall be issued after submission of
remaining deficiencies mentioned at S. No. 32 including correction in A-H form,
Online DPI and submission of three BG’s/DD’s of Rs. 25 lakhs each for
submission of Environment Clearance, Fire Scheme approval and Approved Service
plan and Estimates within the timeframe mentioned above. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
| 21-Sep-2026 |
Sh.
Ashish Kush, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed
about the facts of the case.
Sh.
Krishan Kumar (AR) is present on behalf of the promoter.
The AR
of the promoter states that the reply to the remaining deficiencies has been
submitted today.
The AR
of the Promoter was unable to apprise the Authority of the factual matrix and
the material particulars relating to the application under consideration. In
view thereof, and considering the necessity of having a clear, comprehensive
and factually accurate explanation of the matter, it is considered appropriate
that the Director of the company, along with the competent officials conversant
with the facts and records of the case, shall remain present before the
Authority on the next date of hearing. Their presence is considered necessary
to enable the Authority to obtain clarification on the factual and procedural
aspects of the application and to facilitate effective consideration of the
matter.
The
office is directed to examine the reply filed by the promoter and the matter to
come up on 05.10.2026. |
ADJOURNMENT |
View Order |