| 21-Sep-2026 |
Ms. Deepika, Planning
Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of
the case.
Sh. Gautam babbar (AR), Sh.
Vipul Kumar (AR), Sh. Ranjit Bhambhu (AR) & Sh. Anisha Bhandari (AR) are
present on behalf of the promoter.
Sh.
Gautam Wadhwa, Sh. Mukesh Khanna, Sh. Sanjeev Kumar Bhardwaj, and Sh. Jitender
Bhatia are present on behalf of the complainants. The objections raised by the
complainants relate to the validity of the consent given by the allottees and
the alleged impact of the amendment on the rights and interests of the existing
allottees, including changes in density, layout, green areas, open spaces, and
amenities.
The
Authorized Representative of the promoter states that they have applied for
amendment in registration of project pursuant to revision in building plans and
has submitted the latest updated consent of more than 2/3rd of the
existing allottees.
The
AR of the promoter further states that, in Towers 1 to 5, the area of the fire
lobby is deducted from the FAR area and, apart from this, there is no other
change. In Towers 6 to 8, one additional floor is added to each tower, while
two additional floors are added to Tower 9.
It
is further stated by the AR of the promoter that a public notice dated
31.07.2026 was issued inviting objections regarding the proposed amendment to
the project registration. In response, four out of the 1,509 allottees raised
objections regarding the issues mentioned above.
In
response to the objections, the Promoter states that the requisite consent of
more than 2/3rd of the
allottees has been submitted in the Authority, thereby fulfilling the statutory
requirement under Section 14(2)(ii) of the RERA Act. It is further stated that
there is no change in the carpet area, specifications, parking, consideration
or possession timeline of the existing allottees. The revised plans have been
duly examined and structurally certified by the concerned department, and the
objections have been duly considered. After completion of the prescribed
process, final approval of the revised building plans has been granted on
22.06.2026 by DTCP, Haryana.
The
AR of the promoter states that presently the approval of revised service plans
and estimates and revised electrification plan are under process and the said
approval has not yet been obtained as on date. Further, the Authorized
Representative of the promoter undertakes to obtain and submit:
i.
Revised Service
Plans and Estimates within 6 months from the date of grant of amendment in
registration; and,
ii.
Revised
Electrification Plan within 3 months from the date of grant of amendment in
registration.
Further,
he undertakes to submit a Demand Draft/Bank Guarantee amounting to Rs. 25
lakhs, as a security deposit for timely compliance with the above requirements
at point (i). It is also
expressly
undertaken that in the event of failure to obtain and submit the aforesaid
approval within the stipulated time frame, the said security amount shall be
liable to be forfeited by the Authority.
The
Authority has taken note of the submissions made by the Authorized
Representative of the promoter regarding the non-availability of the aforesaid
statutory approvals as on date. In view of the above, and in the interest of
regulatory compliance, the Authority hereby directs that the promoter shall
submit a Demand Draft/Bank Guarantee, amounting to Rs 25,00,000/- (Rupees
Twenty-Five Lakhs only), in favour of the Authority, as security amount for
timely submission of Revised Service Plans and Estimates within the time period
mentioned above. In the event of non-submission of the above approval within
the prescribed time frame, the corresponding security amount shall stand
forfeited by the Authority, and such failure may also attract additional
regulatory action as permissible under the Act of 2016, rules and regulations
made thereunder. Further, the promoter shall submit the revised Electrification
Plan within the time period mentioned above.
The
AR of the promoter requests to grant amendment in registration of the project after
adding extension of four months granted by the Authority vide order dated
11.08.2026.
Insofar as the allegation regarding two-third consent is concerned, it is
important to go through the relevant provision of the Act which is reproduced
as under:
“14. Adherence to sanctioned
plans and project specifications by the promoter
(1) …
(2) Notwithstanding
anything contained in any law, contract or agreement, after the sanctioned
plans, layout plans and specifications and the nature of the fixtures,
fittings, amenities and common areas, of the apartment, plot or building, as
the case may be, as approved by the competent authority, are disclosed or
furnished to the
person who agree
to take one or more of the said apartment, plot or building, as the case may
be, the promoter shall not make-
(i) …
(ii) any other
alterations or additions in the sanctioned plans, layout plans and
specifications of the buildings or the common areas within the project without
the previous written consent of at least two-thirds of the allottees, other
than the promoter, who have agreed to take apartments in such building.”
It is observed that the total number of allottees in the present
project are 1509 and the promoter has submitted written consent of 1110 unique
allottees which is far more than the statutory requirement of two-third consent
as per section 14(2)(ii) of the Act. Even if the objections of all 4 objecting
allottees are excluded from the consent count, the promoter would still have 1106
valid consents. This remains higher than the statutory threshold and the
requirement under the Act, therefore, stands complied with.
Further,
with regard to the objections raised by the allottees seeking individual
relief, the applicants may seek appropriate relief under the Act of 2016 by
filing a complaint under Section 31 of the Act of 2016 before the Authority, in
the prescribed form and along with the prescribed fee, whereupon the Authority
may initiate further proceedings as deemed appropriate.
Approved
as proposed, subject to rectification of the deficiencies mentioned above at S.
No. 44, including submission of a notarized affidavit from the CEO/Director/MD
regarding the genuineness and originality of the consent. The amendment in
registration is without prejudice to the rights of the existing allottees under
the provisions of Act of 2016, Rules and Regulations made thereunder. The
Authority noted that the promoter is entitled to the benefit of additional
period of four (4) months in view of the Office Order dated 11.08.2026,
accordingly, the benefit of the said 4 months period be incorporated in the
certificate.
The
Addendum Certificate shall be issued after submission and rectification of the
remaining deficiencies mentioned above, including correction of Form REP-I
(Part A–H), updating of the Online DPI, submission of a notarized affidavit
regarding the genuineness and originality of the consent and revised documents
including REP-II, and submission of a DD/BG of Rs 25 lakh towards submission of
the Revised Service Plans and Estimates within the timeframe mentioned above. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |