| 12-Oct-2026 |
Ms.
Deepika, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed
about the facts of the case.
Sh.
Sanju (Director) and Sh. Charan Das (AR) are present on behalf of the promoter.
The
Director of the promoter company submits that the project is being developed
over an area measuring 9.684 acres in two phases, both of which have already
been registered. The promoter has applied for amendment of the registration of
Phase-1, registered vide Registration Certificate No. 104 of 2024, pursuant to
the revision in the building plans of the said phase. The Director of the
promoter submits that Phase-1 comprises Towers A, B, C and D, and Commercial
Blocks 1 and 2. It is submitted that the proposed revisions are limited to the
commercial blocks, while the building plans of the remaining towers remain
unchanged. The Director further submits that pursuant to the revised plans, the
number of shops in Commercial Block 1 has increased from 39 to 63, whereas in
Commercial Block 2, the number of shops has been reduced from 60 to 38, with
the addition of 108 service apartments. Accordingly, the promoter has submitted
the consents of more than two-thirds of the unique allottees for the proposed
amendment.
Further,
the Director of the promoter company submits that the application for amendment
of the registration of Phase-1 was submitted before the Authority on 19.08.2026
in compliance with the directions issued by the Authority vide order dated
18.05.2026.
In
view of the above, the Director of the promoter company requests the Authority
to approve the amendment of registration of the project , submitting that all
requisite approvals are in place and that the remaining minor
deficiencies/documents shall be submitted before the issuance of addendum
certificate under section 4 of the Act, 2016.
The
Authority observes that the present application pertains to the proposed
amendments in the building plans of the commercial blocks, involving a change
in the number of shops and the provision of service apartments, as detailed
above.
Accordingly,
the amendment of registration of the project is approved as proposed. The
Addendum Certificate shall be issued subject to the submission of the remaining
deficiencies/documents mentioned above at Sr. No. 46, including the requisite
corrections in Forms A to H and the online DPI. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |