| 07-Sep-2026 |
Sh. Sumeet, Engineering Officer and Ms. Asha,
Chartered Accountant briefed about the facts of the case.
Sh. Sandip Pandit, Sh. Gaurav Aggarwal, Sh.
Amit Kaushik, Sh. Chaitanya Vats, Sh. Himanshu Gupta and Sh. Sushil Kumar
(AR’s) are present on behalf of the promoter.
The Authorized Representative of the promoter
states that they have submitted an affidavit affirming that if any, claim
arises in respect of any booking/sale etc. by the erstwhile promoters, the
applicant promoter shall be responsible for the same. Further, water connection
and assurance for sewerage connection have been obtained for 14 acres licensed
land and the said assurance/connection shall cater the requirement for complete
license area for the project.
He further states that the environment
clearance, fire scheme approval, service plan and estimates approval, approved
electrification plan, road access permission and mining permission are under
process, and the said approvals have not yet been obtained as on date. Further,
the Authorized Representative of the promoter undertakes to obtain and submit:
i.
Environment clearance, fire scheme approval, service plan and
estimates approval within 6 months from the date of grant of registration;
ii.
Approved Electrification plan and road access permission
within 6 months from the date of grant of registration; and
iii. Mining permission before
start of construction of project.
Further, he undertakes to submit
three separate BG amounting to Rs. 25 lakhs each, as a security deposit for
timely compliance with the above requirements at point (i). It is also
expressly undertaken that in the event of failure to obtain and submit the aforesaid
approval within the stipulated time frame, the said security amount shall be
liable to be forfeited by the Authority.
The Authority has taken
note of the submissions made by the AR of the promoter regarding the
non-availability of the aforesaid statutory approvals as on date. In the event
of non-submission of the above approval within the prescribed time frames, the corresponding
security amount shall stand forfeited by the Authority, and such failure may
also attract additional regulatory action as permissible under the Act of 2016,
rules and regulations made thereunder. Further, the promoter shall submit:
1. Approved electrification
plan and road access permission within 6 months from the date of grant of
registration;
2. Mining permission before
start of construction of project.
With regard to no
booking/sale by Erstwhile promoter, the applicant promoter is directed to
submit the revised affidavit from the director/managing director of the
promoter company.
Approved as proposed
subject to rectification of deficiencies mentioned above. This is without
prejudice to rights of existing allottees u/s 18 of the Act of 2016. Further, a
condition to the effect of submission made in the affidavit by the applicant
promoter regarding no booking/sale by Erstwhile promoter, shall also the
incorporated in the registration certificate.
The Registration Certificate shall be
issued after submission of correction in Form A–H, correction in online DPI,
and Affidavit of director/managing director, along with the other remaining
deficiencies mentioned at S. No. 36. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
| 31-Aug-2026 |
Sh. Sumeet, Engineering Officer and Ms. Asha,
Chartered Accountant briefed about the facts of the case.
Sh. Sandip Pandit, Sh. Gaurav Aggarwal, Sh.
Amit Kaushik, Sh. Chaitanya Vats, Sh. Himanshu Gupta and Sh. Sushil Kumar
(AR’s) are present on behalf of the promoter.
The Authorized Representative (AR) of the
promoter detailed the title of the project land from inception to till date
along with sale of apartments in Phase 1 as well as consent of two-third
allottees. The AR of the promoter further states that they have submitted the
partial reply to the deficiencies pointed out by the Authority and will submit
the remaining deficit documents within two days.
In view of the above, the promoter is directed
to submit the deficit documents along with the detailed representation as
enunciated by the AR of the promoter today during hearing with respect to the title
chain of the project land as well as history of licenses involved in the said
project.
Further, the concerned official is directed to
visit the site of the project including the Phase 1 which is alleged to be
delivered to the allottees by the promoter herein.
The matter is adjourned and to come up on
07.09.2026. |