| 13-Jul-2026 |
Sh. Sumeet, Engineering Officer and Sh. Ashish Dubey, Chartered
Accountant briefed about the facts of the project.
Sh. Abhijeet Singh (AR), Sh. Manik Sharma (AR) and Sh. Bharat Vigmal
(AR) are present on behalf of the promoter.
The Authorized Representative of the promoter states that the
construction works for completion of the project are in full swing and as on
date structure work upto 10th floor has been completed & progressing
further along with finishing works on project site. The AR of the promoter
request to grant an extension of registration of project for one year under
Section 6 of the Act, 2016 for completion of the pending works in the project.
In view of the above, approved as proposed subject to submission of
remaining deficiencies mentioned above as Remarks at S. No. 44. The extension
of registration certificate shall be issued after submission of documents mentioned
at S. No. 44. |
EXTENSION APPROVED |
View Order |