| 06-Jul-2026 |
Ms. Deepika,
Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the
facts of the project.
Sh. Saurabh
Gupta (Partner), Sh. Piyush Agarwal (CEO), Sh. Abhishek Gupta (AR) & Sh.
Vijay Sharma (AR) are present on behalf of the promoter.
The Authorized
Representative (Designated Partner) of the promoter submits that an application
dated 02.06.2026 has been submitted in the Authority seeking amendment of the
existing Registration Certificate No. 31 of 2025 dated 27.03.2025, which is
valid up to 17.04.2027 (as per the declared timeline for completion of the
project under Section 4(2)(l)(C) of the Act, 2016) due to revision in the
building plans. Presently expansion of Environment Clearence, Revised Fire
Scheme Approval and Revised service plans and estimates have not yet been
obtained as on date. Further, the Authorized Representative of the promoter undertakes to
obtain and submit:
i.
Expansion of Environment Clearence, Revised Fire
Scheme Approval and Revised Service Plans and Estimates within 6 months from
the date of grant of addendum to registration Certificate.
Further, he
undertakes to submit three Demand Drafts/Bank Guarantees amounting to Rs 25
lakhs each, as a security deposit for timely compliance with the above
requirements at point (i). It is also expressly undertaken that in the event of
failure to obtain and submit the aforesaid approvals within the stipulated time
frames, the corresponding security amount(s) shall be liable to be forfeited by
the Authority.
The Authority has
taken note of the submissions made by the Authorized Representative of the
promoter regarding the non-availability of the aforesaid statutory approvals as
on date. In view of the above, and in the interest of regulatory compliance,
the Authority hereby directs that the promoter shall submit three separate
Demand Drafts/Bank Guarantees, each amounting to Rs 25,00,000/- (Rupees
Twenty-Five Lakhs only), in favour of the Authority, as security amounts for
timely submission of the following approvals:
a. Expansion of
Environment Clearence: within 6 months from the date of grant of addendum to
registration Certificate.
b. Revised Fire
Scheme Approval: within 6 months from the date of grant of addendum to
registration Certificate
c. Revised Service
Plans and Estimates: within 6 months from the date of grant of addendum to
registration Certificate
In the event of
non-submission of any of the above approvals within the prescribed time frames,
the corresponding security amount shall stand forfeited by the Authority, and
such failure may also attract additional regulatory action as permissible under
the Act of 2016, rules and regulations made thereunder.
Approved
as proposed subject to rectification of deficiencies mentioned above at S. No 40.
The addendum to
registration Certificate shall be issued after submission of remaining
deficiencies mentioned at S. No 40 including correction in A-H form, Online DPI
and submission of three BG’s/DD’s of Rs 25 lakhs each for submission of Expansion
of Environment Clearence, Revised Fire Scheme approval and Revised Service plan
and Estimates within the timeframe mentioned above. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |