| 13-Jul-2026 |
Proceedings dated: 13.07.2026Ms. Prachi Singh, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about thefacts of the project.Sh. Rahul Yadav (Authorized Signatory) and Sh. Manish Kumar (Finance Head) are present on thebehalf of the promoter.The Authorized Representative of the promoter states that the construction work of the project isapproximately 90% complete as on date, and the electrification work and MEP works are currently inprogress. Further, the AR states that the remaining works in the project will be completed within oneyear.In view of the above, approved as proposed, subject to submission of the remaining deficienciesmentioned above under Remarks at Sr. No. 44. The extension of the registration certificate shall beissued only after submission of the documents mentioned at Sr. No. 44. |
EXTENSION APPROVED |
View Order |