| 22-Jun-2026 |
Ms. Nikita Mittal, Planning
Executive and Ms. Asha, Chartered Accountant briefed about the facts of the
project.
Sh. Anil Kumar (Director) and
Sh. Harshal Bhardwaj are present on behalf of promoter.
The Authorized Representative
of the promoter states that the road access permission granted by NHAI vide
letter dated 21.05.2025 has been expired and is required to be renewed by the
competent authority. The promoter further informs that the process for
obtaining an extension/renewal of the said access permission from NHAI has
already been initiated. Further, the Authorized Representative of the promoter
states that a 33 KV HT line is presently passing through the project site and
necessary steps have been undertaken with the concerned department for shifting
the HT line underground and further undertakes to deposit the cost estimates
for the same as when it is conveyed by the concerned department.
The Authorized Representative
of the promoter further submits that presently Fire Scheme Approval and
approved service plans and estimates have not yet been obtained as on date.
Further, the AR of the promoter undertakes to obtain and submit:
i. Fire Scheme Approval and Approved Service Plans and Estimates within
4 months from the date of grant of registration; ii. Mining permission before the commencement
of construction work at the project site; andiii. Revalidated Road access permission from NHAI
within 6 months from the date of grant of registration.Further, he undertakes to
submit two Demand Drafts/Bank Guarantees amounting to Rs. 25 lakhs each, as a
security deposit for timely compliance with the above requirements at point no.
(i). It is also expressly undertaken that in the event of failure to obtain and
submit the aforesaid approvals within the stipulated time frames, the said
security amount(s) shall be liable to be forfeited by the Authority.The Authority has taken note
of the submissions made by the Authorized Representative of the promoter
regarding the non-availability of the aforesaid statutory approvals as on date.
In view of the above, and in the interest of regulatory compliance, the Authority
hereby directs that the promoter shall submit two separate Demand Drafts/Bank
Guarantees, each amounting to Rs. 25,00,000/- (Rupees Twenty-Five Lakhs only),
in favour of the Authority, as security amount(s) for timely submission of Fire
Scheme Approval and Approved Service Plans and Estimates within 4 months from
the date of grant of registration.In the event of
non-submission of any of the above approvals within the prescribed time frames,
the corresponding security amount(s) shall stand forfeited by the Authority,
and such failure may also attract additional regulatory action as permissible
under the Act of 2016, rules and regulations made thereunder. The mining
permission shall be submitted before the commencement of construction work at
the project site, revalidated road access permission from NHAI within 6 months
from the date of grant of registration and cost estimates and relevant details
pertaining to the proposed shifting of the 33 KV HT line passing through the
project site. Approved as proposed subject
to rectification of deficiencies mentioned above at S. No. 33.
The Registration Certificate
shall be issued after submission of corrections in A-H form, Online DPI along
with the other remaining deficiencies mentioned at S. No. 33 and submission of
two DD’s/BG’s of Rs. 25 lakhs each for submission of Fire Scheme approval and
Approved Service Plans and Estimates within the timeframe mentioned above. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |