| 20-Apr-2026 |
Sh. Ashish Kush, Planning Executive and Ms. Asha, Chartered Accountant
briefed about the facts of the case.
None is present on behalf of the complainant. However, complainant in its
objection states as per the original Builder Buyer Agreement (BBA) and the
initial RERA registration, the project was promised to be completed much
earlier. Repeated extensions cause significant financial and mental hardship to
the allottees. The promoter has not provided a clear, tower-wise breakdown of
the pending finishing works or a definitive timeline for the Occupancy
Certificate (OC) application. Currently he is paying house rent due to the delay
in possession. Any further extension without a penalty clause is detrimental to
our interests. Further, the complainant requests the following reliefs:
i.
to direct the promoter a
verified, stage wise construction schedule for the remaining works.
ii.
Ensure that any extension granted is strictly
subject to the payment of Delay Possession Charges (DPC) as per the RERA Act,
2016, from the original promised date of possession until the actual date of
handover.
iii.
Direct the promoter to complete the OC application
for Phase 1 within a fixed, non-extendable timeframe.
Sh. Abhijeet Singh, Sh. Manik Sharma and Sh. Bharat Vigmal are present on
behalf of the promoter and states that the construction/ internal development
works are in progress and are in advance stage of completion. Further, states that
the delay occured due to multiple bans on construction/ development and related
activities were imposed by the National Green Tribunal (NGT), Commission for
Air Quality Management in National Capital Region and Adjoining area. As a
result of these restrictions, the project’s progress did not proceed as planned.
The Authority has
taken note of the submissions made by the Authorized Representative of the
promoter regarding the completion of pending works and reasons for the delay in
completion of the project.
With respect to the
grievances raised by the complainants regarding delay in possession, financial
hardship, and lack of clarity on timelines, the Authority observes that such issues
involve individual contractual disputes between the allottee(s) and the
promoter, which require adjudication based on specific facts, agreements, and
evidence on a case-to-case basis. The Authority holds that such reliefs,
including delay possession charges (DPC), compensation, or enforcement of
specific contractual obligations, cannot be adjudicated in the present
proceedings. Accordingly, the allottee is at liberty to seek appropriate remedy
by instituting separate complaint in accordance with the provisions of the Act,
2016 and the rules framed thereunder. Insofar as the stage wise construction
schedule for the remaining works is concerned, the Authorized Representative of
the promoter is directed to provide a verified stage-wise construction schedule
for the remaining works and to complete the same within the timeline specified
in the extension sought.
In view thereof, the
Authority directs the promoter to complete the remaining works within the
period declared under Section 4(2)(l)(C) of the Act and to obtain the requisite
completion certificate as per applicable law. Consequently, the generalized
allegations raised by the complainants do not merit consideration in the
present proceedings and stand disposed of, leaving it open to the aggrieved parties
to avail remedies in accordance with law. The complaint, to that extent, is
accordingly disposed of.
Approved as proposed, subject to submission of corrected online DPI.
The Extension of Registration Certificate shall
be issued after submission of corrected online DPI. |
EXTENSION APPROVED |