Comprehensive Project Details
Project Location Details
Project Name Project Location Project District Project Tehsil Promoter Name
NANDAKA VILLAGE SIHI, SECTOR-84 GURUGRAM Gurgaon GANGA GLOBAL HOMESPRIVATE LIMITED
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
Not Yet Approved/Certificate Not Uploaded Yet RERA-GRG-2183-2026 13-Mar-2026 13-Mar-2026 APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS NOT REQUIRED Yes 02-Apr-2026 Online, email, by hand Deficiency notice
First Hearing View Form(A-H)
Project Listing Details
Date of Hearing Proceedings of the day Status Order
07-Sep-2026 Sh. Sumeet, Engineering Officer and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the project. Sh. Rahul Mangla (Advocate), Sh. Neeraj Kumar Mishra (Director) and Sh. Mohit Garg (MD) are present on behalf of the promoter. Sh. Satbir Singh, Sh. Raj Kumar Gupta and a number of other allottees of the project are present in person during hearing. The Authorized Representative of the promoter states that they have applied for amendment in registration of project pursuant to revision in building plans for the project. The promoter has also submitted the latest updated consent of more than 2/3rd of the existing allottees including the allottees who have filed objection herein but not all the objector allottees. The AR of the promoter further states that the matter is under discussion and meetings are being arranged from time to time with remaining objector allottees and further undertakes to address the grievance/objections of the remaining objector allottees in order to protect the interest of all existing allottees as mandated under the provisions of the RERA Act 2016. The Authorized Representative of the promoter states that presently the approval of revised service plans and estimates and Mining Permission are under process and the said approval has not yet been obtained as on date. Further, the Authorized Representative of the promoter undertakes to obtain and submit: i.       Revised Service Plans and Estimates within 6 months from the date of grant of amendment in registration; and, ii.    Minig permission for remaining excavation works prior to start of further excavation work.   Further, he undertakes to submit a Demand Draft/Bank Guarantee amounting to Rs. 25 lakhs, as a security deposit for timely compliance with the above requirements at point (i). It is also expressly undertaken that in the event of failure to obtain and submit the aforesaid approval within the stipulated time frame, the said security amount shall be liable to be forfeited by the Authority. The Authority has taken note of the submissions made by the Authorized Representative of the promoter regarding the non-availability of the aforesaid statutory approvals as on date. In view of the above, and in the interest of regulatory compliance, the Authority hereby directs that the promoter shall submit a Demand Draft/Bank Guarantee, amounting to Rs. 25,00,000/- (Rupees Twenty-Five Lakhs only), in favour of the Authority, as security amount for timely submission of Revised Service Plans and Estimates within the time period mentioned above. In the event of non-submission of the above approval within the prescribed time frame, the corresponding security amount shall stand forfeited by the Authority, and such failure may also attract additional regulatory action as permissible under the Act of 2016, rules and regulations made thereunder. Further, the promoter shall submit the Mining permission before start of further excavation work at project site.   The Authority has noted that at the time of application for amendment in registration of project, the promoter has extended the timeline for completion of the project already declared at the time of initial registration of the project under Section 4(2)(l)(C) of the Act, 2016. The Authority observes that the date of completion declared by the Promoter under Section 4(2)(l)(C) of the Act is not a mere procedural or administrative declaration. It constitutes a statutory commitment of the Promoter and forms an essential component of the registration granted under the Act. The declared timeline is intended to provide certainty to the allottees regarding completion and handing over of the project and is intrinsically connected with the statutory obligations of the Promoter under the Act. It is pertinent to mention here that the third party rights in favour of the allottees have already been created in the project on the basis of the declared completion timeline and the timeline under section 4(2)(l)(C) of the Act cannot be unilaterally altered by the promoter. Permitting such an extension through an amendment application would defeat the statutory object of the Act and would adversely affect the legitimate expectations and rights of the existing allottees. An application for amendment cannot be used to dilute, circumvent or override the completion obligation undertaken by the Promoter at the time of registration as per the provisions of the Act. In view of the above, and particularly considering that the Promoter has already created third-party rights in the project, the Authority is of the considered view that the completion timeline declared at the time of initial registration under Section 4(2)(l)(C) of the Act ought to be maintained in the interest of the existing allottees. Accordingly, the request of the Promoter seeking extension of the declared completion date through amendment of the registration cannot be acceded to. Therefore, the promoter is directed to submit the revised REP-II with completion date as already declared while granting registration of project. Approved as proposed subject to rectification of deficiencies mentioned above at S. No. 33. The amendment in registration is without prejudice to the rights of the existing allottees under the provisions of Act of 2016, Rules and Regulations made thereunder. The addendum certificate shall be issued after submission of remaining deficiencies mentioned above including correction in form REP-I (Part A-H), Online DPI, and submission of a DD/BG of Rs. 25 lakhs for submission of Revised Service Plans and Estimates within the timeframe mentioned above. APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS View Order
24-Aug-2026 The matter is adjourned for 07.09.2026. ADJOURNMENT View Order
20-Jul-2026 Sh. Sumeet, Engineering Officer and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the project. Sh. Rahul Mangla (Advocate) and Sh. Mohit Garg (Director) are present on behalf of the promoter. Sh. Arsh Mehta (Advocate for objectors), Sh. Raj Kumar Gupta, Sh. Prashant Rajpal and a number of other allottees of the project are present in person. The AR of the Promoter requests for the last opportunity to submit the consent of allottees regarding the revision of building plans for the project. The counsel for the complainant allottees/allottees presents in person have no objection in this regard. In view of the above submission, the authority grants four weeks’ time to conclude the objections of the allottees and also submit the deficit documents as already conveyed along with the consent of 2/3rd existing allottees of the project including the objectors mentioned herein. Final opportunity is granted to the promoter to comply with the aforesaid directions as well as the provisions of the RERA, 2016 failing which the present application for amendment of registration filed by the promoter may be rejected. The matter is adjourned and to come up on 24.08.2026. ADJOURNMENT View Order
22-Jun-2026 The matter is adjourned to 20.07.2026. ADJOURNMENT View Order
25-May-2026 Sh. Sumeet, Engineering Officer and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the project. Ms. Kadambari Singh (Sr. Advocate), Sh. Rahul Mangla (Advocate) and Sh. Mohit Garg (Director) are present on behalf of the promoter. Sh. Arsh Mehta (Advocate for objectors), Sh. Navin Dhingra, Sh. Sunil Mehta and a number of other allottees of the project are present in person. The complainant allottees present in person submits that discussions are underway with the developer/promoter regarding the revision of building plans for the project. The developer/promoter also acknowledges that discussions with the allottees are ongoing and efforts are being made to arrive at a conclusion in the matter and requests for some reasonable time. In view of the above submission, the authority grants four weeks’ time to conclude the objections of the allottees and also submit the deficit documents as conveyed. The matter to come up on 22.06.2026. ADJOURNMENT View Order
27-Apr-2026 Sh. Sumeet, Engineering Officer and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the project. Ms. Kadambari Singh (Sr. Advocate), Sh. Rahul Mangla (AR) and Sh. Mohit Garg (Director) are present on behalf of the promoter. Sh. Arsh Mehta (Advocate for objectors), Sh. Satbir Singh and a number of other allottees of the project are present. It is pertinent to mention here that multiple objections have been received from the existing allottees of the project against the proposed amendment of registration and revised project configuration. The objecting allottees present in person submits that the promoter had initially advertised and sold units in the project representing it as an ultra-luxury, low-density development with clear landscaping, unobstructed views, privacy, and exclusive leisure, club, and commercial facilities. However, it was submitted that the promoter has now revised the building plans, resulting in increased density, alterations in tower design and layout, and other consequential impacts. It was further contended that no consent was obtained from the allottees regarding such revision of building plans. The allottees have also raised concerns regarding extension of project timelines, alleged lack of transparency and non-disclosure of revised plans and specifications. The Senior Advocate present on behalf of the promoter states that the revised building plans have already been approved by the competent authority i.e., DTCP Haryana after submission of consent of more than two-third existing allottees of the project before DTCP. Copies of such consents have also been placed on record before this Authority. It is further submitted that the revised proposal enhances the residential component from 70% to 95%, reduces the commercial component from 30% to 5% along with increased green area and other changes. The comparative list showing changes along with other deficiencies has been submitted in the Authority on 24.04.2026. The office to examine the same. The learned counsel further seeks four weeks’ time for submission of remaining documents and compliances. The Authority has considered the submissions made on behalf of the promoter, the record available on file including the objections received from allottees, revised building plan approval and documents submitted by the promoter. The Authority also notes that although the promoter has submitted certain consent letters purportedly from 102 allottees out of 119 sold units, the consents placed on record prima facie appear to be in relation to inclusion of additional land and do not clearly and specifically disclose informed consent of the allottees regarding the revision building plans. Moreover, a large number of objections have been received regarding the application for amendment of the project registration pursuant to the revision of building plans. In view of the above, the Authority directs the promoter to submit clear and specific consents from the allottees of the project with respect to the revision of building plans along with other deficit documents including deficit fees. The matter is adjourned and to come up on 25.05.2026. ADJOURNMENT View Order
20-Apr-2026 The matter is adjourned to 27.04.2026. ADJOURNMENT View Order
06-Apr-2026 The matter is adjourned to 20.04.2026. EXAMINATION BY AUTHORITY View Order