| 07-Sep-2026 |
Sh. Sumeet, Engineering Officer and Sh. Ashish
Dubey, Chartered Accountant briefed about the facts of the project.
Sh. Rahul Mangla (Advocate), Sh. Neeraj Kumar
Mishra (Director) and Sh. Mohit Garg (MD) are present on behalf of the
promoter.
Sh. Satbir Singh, Sh. Raj Kumar Gupta and a
number of other allottees of the project are present in person during hearing.
The Authorized Representative of the promoter
states that they have applied for amendment in registration of project pursuant
to revision in building plans for the project. The promoter has also submitted
the latest updated consent of more than 2/3rd of the existing
allottees including the allottees who have filed objection herein but not all the
objector allottees. The AR of the promoter further states that the matter is
under discussion and meetings are being arranged from time to time with
remaining objector allottees and further undertakes to address the
grievance/objections of the remaining objector allottees in order to protect
the interest of all existing allottees as mandated under the provisions of the
RERA Act 2016.
The Authorized Representative of the promoter states
that presently the approval of revised service plans and estimates and Mining
Permission are under process and the said approval has not yet been obtained as
on date. Further, the Authorized Representative of the promoter undertakes to
obtain and submit:
i.
Revised Service
Plans and Estimates within 6 months from the date of grant of amendment in
registration; and,
ii.
Minig permission
for remaining excavation works prior to start of further excavation work.
Further, he undertakes to submit a Demand
Draft/Bank Guarantee amounting to Rs. 25 lakhs, as a security deposit for
timely compliance with the above requirements at point (i). It is also
expressly undertaken that in the event of failure to obtain and submit the
aforesaid approval within the stipulated time frame, the said security amount
shall be liable to be forfeited by the Authority.
The
Authority has taken note of the submissions made by the Authorized
Representative of the promoter regarding the non-availability of the aforesaid
statutory approvals as on date. In view of the above, and in the interest of
regulatory compliance, the Authority hereby directs that the promoter shall
submit a Demand Draft/Bank Guarantee, amounting to Rs. 25,00,000/- (Rupees
Twenty-Five Lakhs only), in favour of the Authority, as security amount for
timely submission of Revised Service Plans and Estimates within the time period
mentioned above. In the event of non-submission of the above approval within
the prescribed time frame, the corresponding security amount shall stand
forfeited by the Authority, and such failure may also attract additional
regulatory action as permissible under the Act of 2016, rules and regulations
made thereunder. Further, the promoter shall submit the Mining permission before start of
further excavation work at project site.
The Authority has noted that at the time of
application for amendment in registration of project, the promoter has extended
the timeline for completion of the project already declared at the time of
initial registration of the project under Section 4(2)(l)(C) of the Act, 2016. The Authority observes
that the date of completion declared by the Promoter under Section 4(2)(l)(C)
of the Act is not a mere procedural or administrative declaration. It
constitutes a statutory commitment of the Promoter and forms an essential
component of the registration granted under the Act. The declared timeline is
intended to provide certainty to the allottees regarding completion and handing
over of the project and is intrinsically connected with the statutory
obligations of the Promoter under the Act. It is pertinent to mention here that
the third party rights in favour of the allottees have already been created in
the project on the basis of the declared completion timeline and the timeline
under section 4(2)(l)(C) of the Act cannot be unilaterally altered by the
promoter. Permitting such an extension through an amendment application would
defeat the statutory object of the Act and would adversely affect the
legitimate expectations and rights of the existing allottees. An application
for amendment cannot be used to dilute, circumvent or override the completion
obligation undertaken by the Promoter at the time of registration as per the
provisions of the Act. In view of the above, and particularly considering that
the Promoter has already created third-party rights in the project, the
Authority is of the considered view that the completion timeline declared at
the time of initial registration under Section 4(2)(l)(C) of the Act ought to
be maintained in the interest of the existing allottees. Accordingly, the
request of the Promoter seeking extension of the declared completion date
through amendment of the registration cannot be acceded to. Therefore, the promoter is directed to
submit the revised REP-II with completion date as already declared while
granting registration of project.
Approved as proposed subject to rectification
of deficiencies mentioned above at S. No. 33. The amendment in registration is
without prejudice to the rights of the
existing allottees under the provisions of Act of 2016, Rules and Regulations
made thereunder.
The addendum certificate shall be issued after
submission of remaining deficiencies mentioned above including correction in
form REP-I (Part A-H), Online DPI, and submission of a DD/BG of Rs. 25 lakhs
for submission of Revised Service Plans and Estimates within the timeframe
mentioned above. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
| 24-Aug-2026 |
The matter is adjourned for 07.09.2026. |
ADJOURNMENT |
View Order |
| 20-Jul-2026 |
Sh. Sumeet, Engineering Officer and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the project. Sh. Rahul Mangla (Advocate) and Sh. Mohit Garg (Director) are present on behalf of the promoter. Sh. Arsh Mehta (Advocate for objectors), Sh. Raj Kumar Gupta, Sh. Prashant Rajpal and a number of other allottees of the project are present in person. The AR of the Promoter requests for the last opportunity to submit the consent of allottees regarding the revision of building plans for the project. The counsel for the complainant allottees/allottees presents in person have no objection in this regard. In view of the above submission, the authority grants four weeks’ time to conclude the objections of the allottees and also submit the deficit documents as already conveyed along with the consent of 2/3rd existing allottees of the project including the objectors mentioned herein. Final opportunity is granted to the promoter to comply with the aforesaid directions as well as the provisions of the RERA, 2016 failing which the present application for amendment of registration filed by the promoter may be rejected. The matter is adjourned and to come up on 24.08.2026. |
ADJOURNMENT |
View Order |
| 22-Jun-2026 |
The matter is adjourned to 20.07.2026. |
ADJOURNMENT |
View Order |
| 25-May-2026 |
Sh.
Sumeet, Engineering Officer and Sh. Ashish Dubey, Chartered Accountant briefed
about the facts of the project.
Ms. Kadambari Singh (Sr.
Advocate), Sh. Rahul Mangla (Advocate) and Sh. Mohit Garg (Director) are
present on behalf of the promoter.
Sh. Arsh Mehta (Advocate
for objectors), Sh. Navin Dhingra, Sh. Sunil Mehta and a number of other
allottees of the project are present in person.
The complainant allottees present in person submits that discussions are
underway with the developer/promoter regarding the revision of building plans
for the project.
The developer/promoter also acknowledges that discussions with the
allottees are ongoing and efforts are being made to arrive at a conclusion in
the matter and requests for some reasonable time.
In
view of the above submission, the authority grants four weeks’ time to conclude
the objections of the allottees and also submit the deficit documents as
conveyed.
The matter to come up on 22.06.2026. |
ADJOURNMENT |
View Order |
| 27-Apr-2026 |
Sh. Sumeet, Engineering Officer and Sh. Ashish Dubey, Chartered
Accountant briefed about the facts of the project.
Ms. Kadambari Singh (Sr. Advocate), Sh. Rahul Mangla (AR) and Sh. Mohit
Garg (Director) are present on behalf of the promoter.
Sh. Arsh Mehta (Advocate for objectors), Sh. Satbir Singh and a number of
other allottees of the project are present.
It
is pertinent to mention here that multiple objections have been received from
the existing allottees of the project against the proposed amendment of
registration and revised project configuration. The objecting allottees
present in person submits that the promoter had initially advertised and sold
units in the project representing it as an ultra-luxury, low-density
development with clear landscaping, unobstructed views, privacy, and exclusive
leisure, club, and commercial facilities. However, it was submitted that the
promoter has now revised the building plans, resulting in increased density,
alterations in tower design and layout, and other consequential impacts. It was
further contended that no consent was obtained from the allottees regarding
such revision of building plans. The allottees have also raised
concerns regarding extension of project timelines, alleged lack of transparency
and non-disclosure of revised plans and specifications.
The Senior Advocate present on behalf of the promoter states that the revised building plans have already been
approved by the competent authority i.e., DTCP Haryana after submission of
consent of more than two-third existing allottees of the project before DTCP. Copies of such consents have
also been placed on record before this Authority. It is further submitted that
the revised proposal enhances the residential component from 70% to 95%,
reduces the commercial component from 30% to 5% along
with increased green area and other changes. The comparative list showing
changes along with other deficiencies has been submitted in the Authority on
24.04.2026. The office to examine the same. The learned
counsel further seeks four weeks’ time for submission of remaining documents
and compliances.
The Authority has considered the submissions made on
behalf of the promoter, the record available on file including the objections received
from allottees, revised building plan approval and documents submitted by the
promoter. The Authority also notes that although the promoter has submitted
certain consent letters purportedly from 102 allottees out of 119 sold units,
the consents placed on record prima facie appear to be in relation to inclusion
of additional land and do not clearly and specifically disclose informed
consent of the allottees regarding the revision building plans. Moreover, a
large number of objections have been received regarding the application for
amendment of the project registration pursuant to the revision of building
plans.
In
view of the above, the Authority directs the promoter to submit clear and
specific consents from the allottees of the project with respect to the
revision of building plans along with other deficit documents including deficit
fees.
The matter is
adjourned and to come up on 25.05.2026. |
ADJOURNMENT |
View Order |
| 20-Apr-2026 |
The matter is adjourned to 27.04.2026. |
ADJOURNMENT |
View Order |
| 06-Apr-2026 |
The matter is adjourned to 20.04.2026. |
EXAMINATION BY AUTHORITY |
View Order |