| 16-Mar-2026 |
Ms. Deepika, Planning
Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of
the project.
Sh. Sujat Ali (AR), Sh.
Ravinder Saund (Director), Sh. Hardeep Singh (Director) are present on behalf
of promoter.
The Authorized Representative
of the promoter submits that the land applied for registration u/s 4 of the
Act, 2016 is free from any kind of litigation. Accordingly, an affidavit from
the Managing Director to this effect is also being submitted. At present, the fire
Scheme approval, approved service plans and estimates, approved electrification
plan, and final road access permission are under process, and the said
approvals have not yet been obtained as of date. Further, the Authorized
Representative of the promoter undertakes to obtain and submit:
i.
Fire
Scheme approval & approved service plans and estimates within 6 months from
the date of grant of registration;
ii.
Approved
Electrification plan within 6 months from the date of grant of registration;
iii.
Final
road access permission after constructing the access road within the stipulated
timeline i.e. 03.11.2026; and
iv.
Mining
permission shall be submitted before the commencement of construction at the
site.
Further, he undertakes to submit the two
Demand Drafts amounting to Rs. 25 lakhs each, as a security deposit for timely
compliance with the above requirements at point (i). It is also expressly
undertaken that in the event of failure to obtain and submit the aforesaid
approval within the stipulated time frames, the said security amount shall be
liable to be forfeited by the Authority.
The Authority has taken note
of the submissions made by the Director of the promoter regarding the
non-availability of the aforesaid statutory approvals as on date. In view of
the
above, and in the interest of
regulatory compliance, the Authority hereby directs that the promoter shall
submit the two Demand Drafts amounting to Rs. 25,00,000/- (Rupees Twenty-Five
Lakhs only) each, in favour of the Authority as security amounts for timely
submission of fire scheme approval and approved service plans and estimates
within 6 months from the date of grant of registration.
In the event of
non-submission of the above approvals within the prescribed time frames, the
corresponding security amount shall stand forfeited by the Authority, and such
failure may also attract additional regulatory action as permissible under the
Act of 2016, rules and regulations made thereunder. Further, the promoter shall
submit:
1.
Approved
electrification plan within 6 months from the date of grant of registration;
2.
Final
road access permission after constructing the access road within the stipulated
timeline, i.e., 03.11.2026; and
3.
Mining
permission shall be submitted before the commencement of construction at the
site.
Approved as proposed subject
to rectification of deficiencies mentioned above.
The Registration Certificate shall be issued after
submission of the remaining deficiencies mentioned above including correction
in Form A–H, online DPI and submission of two Demand Drafts of Rs. 25,00,000/-
(Rupees Twenty-Five Lakhs only) each for submission of fire scheme approval and
approved service plans and estimates within the time frame mentioned above,
along with the deficiency mentioned at S. No. 33. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |