| Project Name | Project Location | Project District | Project Tehsil | Promoter Name |
|---|---|---|---|---|
| Signature Global City 81(2) | Village Nakhdola,Sector-81, Gurugram | GURUGRAM | STERNAL BUILDCON PRIVATE LIMITED |
| Project Id | Receiving Date | Online Submission Date | Current Status | Next Date of Hearing | Notice Dispatched | Notice Dispatched On | Notice Tracking Id | Notice Dispatched Remarks | View Notice | Initially Scrutinized Remarks |
|---|---|---|---|---|---|---|---|---|---|---|
| RERA-GRG-2169-2026 | 04-Feb-2026 | 04-Feb-2026 | EXTENSION APPROVED | NOT REQUIRED | Not Yet | -- | First hearing |
| Date of Hearing | Proceedings of the day | Status | Order |
|---|---|---|---|
| 26-Feb-2026 | Sh. Ashish Dubey, Chartered Accountant and Ms. Neeraj Gautam, Associate Architectural Executive briefed about the facts of the case. Sh. Vineet Maheshwari (AR), Sh. Vedant Batra (AR) and Sh. Ravinder are present on behalf of the promoter and request for grant of extension under section 6 of the Act of 2016. The AR assures that the remaining deficiencies as pointed by the Authority will be rectified before the issuance of the extension certificate. The Authority has taken note of the submissions made by the Authorized Representative of the promoter regarding the submission of remaining documents. The extension of the registration of the project is approved as proposed subject to the rectification of deficiencies mentioned above at S. No 43. The Extension Certificate shall be issued after submission of remaining deficiencies mentioned above. | EXTENSION APPROVED | View Order |
| 23-Feb-2026 | 1. On 23.02.2026, the matter was adjourned to 02.03.2026 which was then preponed to 26.02.2026. | EXAMINATION BY AUTHORITY | View Order |