| 18-Feb-2026 |
Ms. Deepika, Planning
Executive and Ms. Asha, Chartered Accountant briefed about the facts of the
project.
Sh. Varun Sharma (Director),
Sh. Aayush Gaur (Director), Sh. Deepak Sangwan (Director) are present on behalf
of promoter.
Sh. Jagdish Singh is present
on behalf of the landowner.
The Director of the promoter states
that the promoter has applied for registration in collaboration with M/s R.P.
Buildtech. The Director present further clarifies that “Origen Realty” is its
own group company and they are using the brand name in the draft brochure
submitted in the Authority. He also states that the project site is connected
by a 12 m wide road, and further, the 24 m wide road proposed as per the
approved building plans shall be developed by the promoter and undertaking in
this regard, from the director has been submitted in the Authority.
The Director of the promoter submits that, at present,
the environment clearance, fire scheme approval, approved service plans and
estimates, and mining permission are under process, and the said approvals have
not been obtained as on date. He further undertook to obtain and submit:
i.
Environment
clearance within 5 months from the date of grant of registration;
ii.
Fire
scheme approval and Approved service plans & estimates within 3 months from
the date of grant of registration;
iii.
Mining
permission before the start of construction at the site.
Further, he undertakes to submit the three Demand
Drafts amounting to Rs. 25 lakhs each, as a security deposit for timely
compliance with the above requirements at point (i) & (ii). It is also
expressly undertaken that in the event of failure to obtain and submit the
aforesaid approvals within the stipulated time frames, the said security amounts
shall be liable to be forfeited by the Authority.
The Authority has taken note
of the submissions made by the Director of the promoter regarding the
non-availability of the aforesaid statutory approvals as on date. In view of
the above, and in the interest of regulatory compliance, the Authority hereby
directs that the promoter shall submit the three Demand Drafts amounting to Rs.
25,00,000/- (Rupees Twenty-Five Lakhs only) each, in favour of the Authority as
security amounts for timely submission of the environment clearance within 5
months from the date of grant of registration and fire scheme approval and
approved service plans and estimates within 3 months from the date of grant of
registration.
In the event of
non-submission of the above approvals within the prescribed time frames, the
corresponding security amount shall stand forfeited by the Authority, and such
failure may also attract additional regulatory action as permissible under the
Act of 2016, rules and regulations made thereunder. The promoter is directed to
submit a confirmation on the letterhead of “Origen Realty” permitting the
developer to use its brand name in the said project and mining permission shall
be submitted before the start of construction at the site.
Approved as proposed subject
to rectification of deficiencies mentioned above.
The Registration Certificate shall be issued after
submission of the remaining deficiencies mentioned above, including correction
in Form A–H, online DPI, confirmation for use of the brand name on the
letterhead of Origen Realty, and submission of three Demand Drafts of Rs.
25,00,000/- (Rupees Twenty-Five Lakhs only) each for submission of environment
clearance, fire scheme approval, and approved service plans and estimates
within the time frame mentioned above, along with the deficiency mentioned at S.
no. 36. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |