Comprehensive Project Details
Project Location Details
Project Name Project Location Project District Project Tehsil Promoter Name
Bonheur Hub Village - Dhunela, Sector 35 GURUGRAM Sohna CCRK Developers LLP
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/1046/778/2026/18 DATED 11.03.2026 RERA-GRG-2152-2026 06-Jan-2026 05-Jan-2026 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Yes 28-Jan-2026 By hand By hand
First hearing View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/1046/778/2026/18 DATED 11.03.2026 16-Mar-2026 RC Uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
11-Feb-2026 Ms. Deepika, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the project. Sh. Rajeev Gupta (Senior VP), Sh. Yogesh Kumar Sharma (AG), Sh. Narender Kumar (Manager) are present on behalf of the promoter. Sh. Chander Mohan Khatana is present on behalf of the landowner. The Authorized Representative of the promoter submits that presently Approved service plans and estimates and Approved Electrification plan are under process and the said approvals have not yet been obtained as on date. The AR of the promoter further undertakes to obtain and submit: i.     Approved Service Plans and Estimates within 4 months from the date of grant of registration; and ii.   Approved Electrification plan within 4 months from the date of grant of registration.   Further, he undertakes to submit Demand Draft / Bank Guarantee amounting to Rs. 25 lakhs, as a security deposit for timely compliance with the above requirements at point (i). It is also expressly undertaken that in the event of failure to obtain and submit the aforesaid approval within the stipulated time frame, the said security amount shall be liable to be forfeited by the Authority.   The Authority has taken note of the submissions made by the Authorized Representative of the promoter regarding the non-availability of the aforesaid statutory approval as on date. In view of the above, and in the interest of regulatory compliance, the Authority hereby directs that the promoter shall submit Demand Draft / Bank Guarantee, amounting to Rs. 25,00,000/- (Rupees Twenty-Five Lakhs only), in favour of the Authority, as security amount for timely submission of the approved Service Plans and Estimates within 4 months from the date of grant of registration.   In the event of non-submission of the above approval within the prescribed time frame, the corresponding security amount shall stand forfeited by the Authority, and such failure may also attract additional regulatory action as permissible under the Act of 2016, rules and regulations made thereunder.   Approved as proposed subject to rectification of deficiencies mentioned above at S.no. 33.   The Registration Certificate shall be issued after deposition of above DD/BG and rectification of other deficiencies as listed above at S.no. 33. APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS View Order
09-Feb-2026 The matter was adjourned and fixed for 16.02.2026. ADJOURNMENT View Order
02-Feb-2026 The matter was adjourned and fixed for 09.02.2026. EXAMINATION BY AUTHORITY View Order