| 19-Jan-2026 |
Proceedings dated 19.01.2026.
Sh. Shashank Sharma, Associate
Engineer Executive and Ms. Asha, CA briefed about the facts of the project.
Sh. Abhijeet Singh (AR), Sh. Manik Sharma (AR) and Sh.
Bharat Vigmal (AR) are present on behalf of promoter.
The Authorized Representative of the
promoter has submitted that approximately ninety percent (90%) of the
construction work at the project site stands completed and that the remaining
balance works shall be completed within a period of two to three months. Further,
the promoter submitted that, upon completion of the remaining works, the
promoter shall apply for the grant of Occupation Certificate (OC) before the
competent authority.
Approved as proposed.
The Extension of Registration Certificate shall
be issued after submission of corrections in the DPI. |
EXTENSION APPROVED |
View Order |