| 26-Feb-2026 |
Ms. Deepika,
Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the
facts of the case.
Ms. Julie Jha (AR)
& Sh. Vijay Singh (AR) are present on behalf of promoter.
The Authorized
Representative (AR) of the promoter submits that an application dated
16.01.2026 has been filed before the Authority seeking amendment of the
existing Registration Certificate No. 20 of 2020 dated 17.08.2020, which was
extended for a period of one year under Section 6 of the Act, 2016.
Accordingly, the validity of the Registration Certificate is up to 12.05.2026
as on date. The AR further submits that the revised building plans of the said
project were approved by the competent authority on 15.01.2026. As per the
revised approval, the number of floors has been increased from G+26 to G+34,
and the number of dwelling units has been increased from 401 to 449. The
sanctioned FAR has also increased from 61,965.02 sq. m. to 74,859.616 sq. m.
Further, the AR of
the promoter stated that at the time of project registration, the declared
timeline for
completion of the project under Section 4(2)(l)(C) of the Act, 2016 was
13.05.2025, which was subsequently extended under Section 6 of the Act, 2016 up
to 12.05.2026. The AR of the promoter also submitted that, at present the
Revised Fire Scheme Approval and the Approved Revised Service Plans &
Estimates are presently under process and have not yet been obtained as on
date. The AR undertakes to obtain and submit:
i.
Revised Fire Scheme Approval and Approved Revised Service Plans & Estimates
within four months from the date of grant of amendment of registration.
Further, she
undertakes to submit two Demand Drafts/Bank Guarantees amounting to Rs. 25
lakhs each as security deposits for timely compliance with the requirement
mentioned at point (i). It is expressly undertaken that in the event of failure
to obtain and submit the aforesaid approvals within the stipulated timeframe,
the said security amounts shall be liable to be forfeited by the Authority.
The Authority has
taken note of the submissions made by the AR of the promoter regarding the
non-availability of the aforesaid statutory approvals as on date. In view of
the above, and in the interest of regulatory compliance, the Authority hereby
directs the promoter to submit two separate Demand Drafts/Bank Guarantees, each
amounting to Rs. 25,00,000/- (Rupees Twenty-Five Lakhs only), in favour of the
Authority as security amounts for timely submission of the following approval:
a.
Revised Fire Scheme Approval and Approved Revised Service Plans & Estimates
within four months from the date of grant of amendment of registration.
In the event of
non-submission of the above approval within the prescribed timeframe, the
corresponding security amount shall stand forfeited by the Authority, and such
failure may also attract additional regulatory action as permissible under the
Act of 2016 and the rules and regulations made thereunder.
In view of the
above, the Authority decides to register only those units which have been duly
approved by the competent authority, i.e., DTCP, amounting to 449 units as on
date as per the approved revised building plans. The date of completion of the
project shall remain 12.05.2026, as already specified while granting extension
of registration under Section 6 of the Act ibid.
Approved as
proposed, subject to rectification of the deficiencies mentioned above.
The Addendum
Certificate shall be issued after submission of the remaining deficiencies
mentioned above at Sr. No. 48, including correction in Forms A–H, Online DPI,
affidavit regarding the sharing model duly signed by both parties and
submission of two DDs/BGs of Rs. 25 lakhs each for submission of the Revised
Fire Scheme Approval and Approved Revised Service Plans & Estimates within
the timeframe mentioned above. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |