| 20-Apr-2026 |
Ar. Neeraj Gautam, Associate Architectural
Executive and Ms. Asha, Chartered Accountant briefed about the facts of the
project.
Sh. Ashok Singh Jaunapuria
(Director), Sh. Manoj Shukla (AR) and Sh. Sunil Shekhawat (AR) are present on behalf of the promoter.
The Authorized Representative of the promoter
states that presently the approval of revised service plans and estimates,
revised fire scheme and revised environmental clearance are under process and
the said approvals have not yet been obtained as on date. Further, the Authorized
Representative of the promoter undertakes to obtain and submit:
i.
Revised Service
Plans and Estimates within 4 months from the date of grant of amendment in registration;
ii.
Revised Fire
Scheme within 4 months from the date of grant of amendment in registration;
iii.
Revised
Environmental Clearance within 6 months from the date of grant of amendment in registration;
and
iv.
Mining permission
before commencement of excavation.
Further, he undertakes to submit three Demand
Draft/Bank Guarantee amounting to Rs. 25 lakhs each, as a security deposit for
timely compliance with the above requirements at point (i), (ii) and (iii). It
is also expressly undertaken that in the event of failure to obtain and submit
the aforesaid approvals within the stipulated time frame, the said security
amount(s) shall be liable to be forfeited by the Authority.
The
Authority has taken note of the submissions made by the Authorized
Representative of the promoter regarding the non-availability of the aforesaid
statutory approvals as on date. In view of the above, and in the interest of
regulatory compliance, the Authority hereby directs that the promoter shall
submit three Demand Draft/ Bank Guarantee, amounting to Rs. 25,00,000/- (Rupees
Twenty-Five Lakhs only) each, in favour of the Authority, as security amounts
for timely submission of Revised Service Plans and Estimates, Revised Fire
Scheme and Revised Environmental Clearance within the time period mentioned
above. The Mining permission shall be submitted before commencement of
excavation at the site.
In
the event of non-submission of the above approval within the prescribed time
frame, the corresponding security amount(s) shall stand forfeited by the
Authority, and such failure may also attract additional regulatory action as
permissible under the Act of 2016, rules and regulations made thereunder.
Approved as proposed subject to rectification
of deficiencies mentioned above at S. No. 37.
The addendum certificate shall be issued after
submission of remaining deficiencies mentioned above including correction in
form REP-I (Part A-H), Online DPI and submission of three DD/BG of Rs. 25 lakhs
each for submission of Revised Service Plans and Estimates, Revised Fire Scheme
and Revised Environmental Clearance within the timeframe mentioned above. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |