Comprehensive Project Details (Project Extension)
Project Location Details (Project Extension)
Project Name Project Location Project District Project Tehsil Promoter Name
Godrej nature plus Sector-33, sohna, gurugram GURUGRAM Godrej highview llp
Project Detail
Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks
RERA-GRG-2112-2025 10-Nov-2025 10-Nov-2025 EXTENSION APPROVED NOT REQUIRED Yes 25-Nov-2025 By hand Deficiency notice
First hearing
Project Listing Details (Project Extension)
Date of Hearing Proceedings of the day Status Order
29-Dec-2025 Proceedings dated 29.12.2025.Ms. Prachi Singh, Planning Executive and Ms. Asha, Chartered Accountant briefed about the facts of the case.Sh. Ranjit Bhambhu (AR) and Ms. Anjana Kumari (AR) are present on behalf of the promoter and states thatout of 12 towers, Occupation certificate for 3 towers namely G, H, J and EWS has been issued by DTCP,Haryana and at present around 1000 labours are working at the site to complete the remaining work. TheAR further request for grant of extension of registration under Section 6 of the Act, 2016. The AuthorizedRepresentative of the promoter submits that the remaining deficiencies as pointed by the Authority will besubmitted within a period of one week.The AR of the promoter also states that at the time of substitution of the registration certificate in 2021, theRC was issued with the new bank account (changed bank account). Further states that they had changedbank account in the quarter Jan- March, 2019.The Authority has taken note of the submissions made by the Authorized Representative of the promoter forsubmission of remaining documents along with the CA certificate regarding closing balance of old bankaccount and opening balance of new account are same at the time of change in bank account and also tosubmit an affidavit of director regarding the same.The extension of the registration of the project is approved as proposed subject to the rectification ofdeficiencies mentioned above at S.no. 42.The Extension Certificate shall be issued after submission of remaining deficiencies mentioned aboveincluding CA certificate and affidavit of directors. EXTENSION APPROVED View Order
22-Dec-2025 Proceedings dated: 22.12.2025 Ms. Prachi Singh, Planning Executive and Ms. Asha, Chartered Accountant briefed about the facts of the project. Ms. Anjana Gulati (AR) and Sh. Manpreet (AR) are present on the behalf of the promoter. The Promoter's authorized representative states that there are total number of 12 towers out of which Occupation certificate for 3 towers namely G, H, J and EWS has been issued by DTCP, Haryana vide memo no. ZP-1017/JD(RA)/2023/9501 dated 03.04.2023.  The handover of the units for tower no. G has been completed by 60-70%. While possession for remaining two towers H and J will start by Jan 2026. Regarding the remaining nine towers, the superstructure work is complete for three towers, and 40–60% of the work is finished for the remaining six towers.  Interior work is about to begin now. Furthermore, it was stated that delays in the remaining construction were due to disputes and issues with the contractor, which has been resolved.  The Authority has noted these submissions. Consequently, the promoter is directed to provide a comprehensive completion plan for all pending works, along with executed copies of the application forms, allotment letters, Builder-Buyer Agreements (BBA), and conveyance deeds and to rectify the above-mentioned deficiencies at point no.41. The matter to come up on 29.12.2025. ADJOURNMENT View Order
08-Dec-2025 Matter is adjourned to 22.12.2025. ADJOURNMENT View Order
01-Dec-2025 Matter is adjourned to 08.12.2025.  EXAMINATION BY AUTHORITY View Order