| 29-Dec-2025 |
Proceedings dated 29.12.2025.Ms. Prachi Singh, Planning Executive and Ms. Asha, Chartered Accountant briefed about the facts of the case.Sh. Ranjit Bhambhu (AR) and Ms. Anjana Kumari (AR) are present on behalf of the promoter and states thatout of 12 towers, Occupation certificate for 3 towers namely G, H, J and EWS has been issued by DTCP,Haryana and at present around 1000 labours are working at the site to complete the remaining work. TheAR further request for grant of extension of registration under Section 6 of the Act, 2016. The AuthorizedRepresentative of the promoter submits that the remaining deficiencies as pointed by the Authority will besubmitted within a period of one week.The AR of the promoter also states that at the time of substitution of the registration certificate in 2021, theRC was issued with the new bank account (changed bank account). Further states that they had changedbank account in the quarter Jan- March, 2019.The Authority has taken note of the submissions made by the Authorized Representative of the promoter forsubmission of remaining documents along with the CA certificate regarding closing balance of old bankaccount and opening balance of new account are same at the time of change in bank account and also tosubmit an affidavit of director regarding the same.The extension of the registration of the project is approved as proposed subject to the rectification ofdeficiencies mentioned above at S.no. 42.The Extension Certificate shall be issued after submission of remaining deficiencies mentioned aboveincluding CA certificate and affidavit of directors. |
EXTENSION APPROVED |
View Order |
| 22-Dec-2025 |
Proceedings dated: 22.12.2025
Ms. Prachi Singh, Planning Executive and Ms. Asha, Chartered
Accountant briefed about the facts of the project.
Ms. Anjana Gulati (AR) and Sh. Manpreet (AR) are present on
the behalf of the promoter.
The
Promoter's authorized representative states that there are total number of 12
towers out of which Occupation certificate for 3 towers namely G, H, J and EWS
has been issued by DTCP, Haryana vide memo no. ZP-1017/JD(RA)/2023/9501 dated
03.04.2023.
The
handover of the units for tower no. G has been completed by 60-70%. While
possession for remaining two towers H and J will start by Jan 2026.
Regarding
the remaining nine towers, the superstructure work is complete for three
towers, and 40–60% of the work is finished for the remaining six towers. Interior work is about to begin now.
Furthermore,
it was stated that delays in the remaining construction were due to disputes
and issues with the contractor, which has been resolved. The Authority has noted these submissions.
Consequently, the promoter is directed to provide a comprehensive
completion plan for all pending works, along with executed copies of the
application forms, allotment letters, Builder-Buyer Agreements (BBA), and
conveyance deeds and to rectify the above-mentioned deficiencies at point
no.41.
The matter to come up on 29.12.2025. |
ADJOURNMENT |
View Order |