Comprehensive Project Details (Project Extension)
Project Location Details (Project Extension)
Project Name Project Location Project District Project Tehsil Promoter Name
VANYA CITY SECTOR 99A GURUGRAM Betterchoice Realtors Pvt Ltd
Project Detail
Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks
RERA-GRG-2109-2025 03-Nov-2025 03-Nov-2025 EXTENSION APPROVED NOT REQUIRED Yes 20-Nov-2025 FIRST DEFICIENCY NOTICE BY HAND
First hearing
Project Listing Details (Project Extension)
Date of Hearing Proceedings of the day Status Order
16-Mar-2026 Sh. Ashish Kush, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the case. Sh. Ashvin Kumar, Sh. Virendra Kumar, Sh. Sachin Gupta, Sh. Honey Dhawan and Sh. Prateek Gautam are present on behalf of the Complainant and states that the promoter has revised the layout plan without the prior consent of the two-third of the allottees. Revised layout leads to increase in project density which affects amenities and infrastructure. Essential infrastructure – STP, Boundary walls, Electricity and water connections have yet to be commence. It is also submitted that as the project has been delayed, the allottees are entitled for interest as per the provisions of the Act. Further, despite taking the entire sale consideration, the promoter has started demanding additional charges from some of the allottees which does not form part of the BBA executed inter se parties. Further, some of the plot owners have also got their conveyance deed executed. Sh. Masum Kumar, Sh. Praval Jain and Sh. Rajendra Patle are present on behalf of the promoter and states that they have submitted the consents of 132 unique allottees out of 188 unique allottees w.r.t the revision in the layout plan and a public notice to this effect was also published. Presently, Revised Service plans and estimates are under process and the said approval has not yet been obtained as on date. Further, the AR of the promoter undertakes to obtain and submit the same within 4 months from the date of grant of extension certificate. Further, he undertakes to submit a Demand Draft/Bank Guarantee amounting to Rs. 25 lakhs, as a security deposit for timely compliance with the above-said approval. It is also expressly undertaken that in the event of failure to obtain and submit the aforesaid approval within the stipulated time frame, the said security amount shall be liable to be forfeited by the Authority. The Authority has taken note of the submissions made by the Authorized Representative of the promoter regarding the non-availability of the aforesaid statutory approval as on date. In view of the above, and in the interest of regulatory compliance, the Authority hereby directs that the promoter shall submit a Demand Draft/Bank Guarantee, amounting to Rs. 25,00,000/- (Rupees Twenty-Five Lakhs only), in favour of the Authority, as security amount for timely submission of the Revised Service Plans and Estimates within 4 months from the date of grant of extension certificate. In the event of non-submission of the above approval within the prescribed time frame, the security amount shall stand forfeited by the Authority, and such failure may also attract additional regulatory action as permissible under the Act of 2016, rules and regulations made thereunder. Upon consideration of the submissions advanced by the complainants, the Authority is of the view that several issues raised herein such as alleged delay in handing over possession, levy of charges purportedly beyond the terms of the Builder Buyer Agreement (BBA), and execution of conveyance deeds constitute individual grievances which require adjudication on a case-to-case basis. Accordingly, the allottees are at liberty to seek appropriate relief by instituting separate complaints in accordance with the provisions of the Act, 2016 and the rules framed thereunder. Insofar as the allegations regarding incomplete development works, including installation of STP, construction of boundary walls, and provision of electricity and water connections are concerned, the Authorized Representative of the promoter has undertaken to complete the same within the timeline specified in the extension sought. In view thereof, the Authority directs the promoter to complete the remaining development works within the period declared under Section 4(2)(l)(C) of the Act and to obtain the requisite completion certificate as per applicable law. Consequently, the generalized allegations raised by the complainants do not merit consideration in the present proceedings and stand disposed of, leaving it open to the aggrieved parties to avail remedies in accordance with law. The complaint, to the extent raised, is accordingly disposed of. Approved as proposed, subject to submission of the DD/BG amounting to Rs. 25 lakhs as a security amount for submission of Revised Service plan and Estimates within 4 months from the grant of extension of registration certificate and rectification of deficiencies remaining deficiencies mentioned at S. No. 42. The Extension of Registration Certificate shall be issued after submission of remaining deficiencies mentioned at S. 42 including corrections in Online DPI and submission of BG/DD of Rs 25 lakhs for submission of Revised Service plan and Estimates within the timeframe mentioned above. EXTENSION APPROVED View Order
16-Feb-2026 Matter is adjourned to 16.03.2026. ADJOURNMENT View Order
09-Feb-2026 The matter is adjourned and fixed for 16.02.2026. ADJOURNMENT View Order
29-Dec-2025 Sh. Ashish Kush, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the case. Sh. Masum Gupta and Sh. Praval Jain are present on behalf of the promoter. Sh. Ashwin Kumar, Sh. Prateek Gautam, Sh. Honey Dhawan, Sh. Sachin Gupta and Sh. Ketan Saraf are present on behalf of the complainants. The complainants state that the promoter has revised the layout plan without their prior consent. Revised layout leads to increase in project density which affects amenities and infrastructure. Essential infrastructure – STP, Boundary walls, Electricity and water connections have yet to be commence. Further, the promoter has taken the full consideration for plot and some of the plot owners have got their conveyance deed executed. If any extension at this point of time is allowed it will be great injustice to plot owners. Further, stated that if the Authority considers granting an extension, the same must be strictly subject to the conditions of prompt commencement and completion of infrastructure works, regular submission of monthly progress reports along with financial statements, no further revision of layout plans or density without the explicit consent of a majority of the allottees including imposition of penalties in case of delay. The AR of the promoter states that the work at site is in progress and the promoter is committed to deliver the project to the allottees despite the challenges being faced such as high water level, NGT bans etc. The public notice with respect to the consent of the existing allottees regarding revision of layout plan be issued in three prominent newspapers 2 English and 1 Hindi for inviting objections. Meanwhile, the promoter is directed to submit the plan of action for completion of the project alongwith the other deficit documents. Further, a site visit also to be conducted by the Concerned official before the next date of hearing to check the progress on the site. The matter to come up on 09.02.2026. ADJOURNMENT View Order
15-Dec-2025 The matter is adjourned and fixed for 29.12.2025. ADJOURNMENT View Order
24-Nov-2025 The matter is adjourned and fixed for 15.12.2025. EXAMINATION BY AUTHORITY View Order