| 16-Mar-2026 |
Sh. Ashish Kush, Planning Executive and Sh. Ashish Dubey, Chartered
Accountant briefed about the facts of the case.
Sh. Ashvin Kumar, Sh. Virendra Kumar, Sh. Sachin Gupta, Sh. Honey Dhawan
and Sh. Prateek Gautam are present on behalf of the Complainant and states that
the promoter has revised the layout plan without the prior consent of the
two-third of the allottees. Revised layout leads to increase in project density
which affects amenities and infrastructure. Essential infrastructure – STP,
Boundary walls, Electricity and water connections have yet to be commence. It
is also submitted that as the project has been delayed, the allottees are
entitled for interest as per the provisions of the Act. Further, despite taking
the entire sale consideration, the promoter has started demanding additional
charges from some of the allottees which does not form part of the BBA executed
inter se parties. Further, some of the plot owners have also got their
conveyance deed executed.
Sh.
Masum Kumar, Sh. Praval Jain and Sh. Rajendra Patle are present on behalf of
the promoter and states that they have submitted the consents of 132 unique allottees
out of 188 unique allottees w.r.t the revision in the layout plan and a public
notice to this effect was also published. Presently, Revised Service plans and estimates are under process and
the said approval has not yet been obtained as on date. Further, the AR of the promoter
undertakes to obtain and submit the same within 4 months from the date of grant
of extension certificate. Further, he undertakes to submit a Demand Draft/Bank
Guarantee amounting to Rs. 25 lakhs, as a security deposit for timely
compliance with the above-said approval. It is also expressly undertaken that
in the event of failure to obtain and submit the aforesaid approval within the
stipulated time frame, the said security amount shall be liable to be forfeited
by the Authority.
The Authority has
taken note of the submissions made by the Authorized Representative of the
promoter regarding the non-availability of the aforesaid statutory approval as
on date. In view of the above, and in the interest of regulatory compliance,
the Authority hereby directs that the promoter shall submit a Demand Draft/Bank
Guarantee, amounting to Rs. 25,00,000/- (Rupees Twenty-Five Lakhs only), in
favour of the Authority, as security amount for timely submission of the
Revised Service Plans and Estimates within 4 months from the date of grant of
extension certificate.
In the event of
non-submission of the above approval within the prescribed time frame, the
security amount shall stand forfeited by the Authority, and such failure may
also attract additional regulatory action as permissible under the Act of 2016,
rules and regulations made thereunder.
Upon consideration of
the submissions advanced by the complainants, the Authority is of the view that
several issues raised herein such as alleged delay in handing over possession,
levy of charges purportedly beyond the terms of the Builder Buyer Agreement
(BBA), and execution of conveyance deeds constitute individual grievances which
require adjudication on a case-to-case basis. Accordingly, the allottees are at
liberty to seek appropriate relief by instituting separate complaints in
accordance with the provisions of the Act, 2016 and the rules framed thereunder.
Insofar as the allegations regarding incomplete development works, including
installation of STP, construction of boundary walls, and provision of
electricity and water connections are concerned, the Authorized Representative
of the promoter has undertaken to complete the same within the timeline
specified in the extension sought. In view thereof, the Authority directs the
promoter to complete the remaining development works within the period declared
under Section 4(2)(l)(C) of the Act and to obtain the requisite completion
certificate as per applicable law. Consequently, the generalized allegations
raised by the complainants do not merit consideration in the present
proceedings and stand disposed of, leaving it open to the aggrieved parties to avail
remedies in accordance with law. The complaint, to the extent raised, is
accordingly disposed of.
Approved as proposed, subject to submission of the DD/BG amounting to Rs.
25 lakhs as a security amount for submission of Revised Service plan and
Estimates within 4 months from the grant of extension of registration
certificate and rectification of deficiencies remaining deficiencies mentioned
at S. No. 42.
The Extension of Registration Certificate shall be
issued after submission of remaining deficiencies mentioned at S. 42 including
corrections in Online DPI and submission of BG/DD of Rs 25 lakhs for submission
of Revised Service plan and Estimates within the timeframe mentioned above. |
EXTENSION APPROVED |
View Order |
| 29-Dec-2025 |
Sh. Ashish Kush, Planning Executive and Sh. Ashish Dubey, Chartered
Accountant briefed about the facts of the case.
Sh.
Masum Gupta and Sh. Praval Jain are present on behalf of the promoter.
Sh.
Ashwin Kumar, Sh. Prateek Gautam, Sh. Honey Dhawan, Sh. Sachin Gupta and Sh.
Ketan Saraf are present on behalf of the complainants.
The
complainants state that the promoter has revised the layout plan without their
prior consent. Revised layout leads to increase in project density which
affects amenities and infrastructure. Essential infrastructure – STP, Boundary
walls, Electricity and water connections have yet to be commence. Further, the
promoter has taken the full consideration for plot and some of the plot owners
have got their conveyance deed executed. If any extension at this point of time
is allowed it will be great injustice to plot owners. Further, stated that if the Authority considers granting
an extension, the same must be strictly subject to the conditions of prompt
commencement and completion of infrastructure works, regular submission of
monthly progress reports along with financial statements, no further revision
of layout plans or density without the explicit consent of a majority of the
allottees including imposition of penalties in case of delay.
The AR
of the promoter states that the work at site is in progress and the promoter is
committed to deliver the project to the allottees despite the challenges being
faced such as high water level, NGT bans etc.
The
public notice with respect to the consent of the existing allottees regarding
revision of layout plan be issued in three prominent newspapers 2 English and 1
Hindi for inviting objections.
Meanwhile,
the promoter is directed to submit the plan of action for completion of the
project alongwith the other deficit documents. Further, a site visit also to be
conducted by the Concerned official before the next date of hearing to check
the progress on the site.
The
matter to come up on 09.02.2026. |