| 24-Nov-2025 |
Ms. Deepika, Planning
Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of
the case.
Sh.
S.K Kaushik (VP), Sh. Mukesh Tripathi (AR) & Sh. Ajay Gupta (AR) are
present on behalf of the promoter.
The
AR of the promoter proposes to submit the DD/BGs of Rs. 25 lakhs each as
security to submit the Environment clearance & Fire scheme approval within
6 months of grant the registration. It is also
expressly
undertaken that in the event of failure to obtain and submit the aforesaid
approvals within the stipulated time frames, the said security amount(s) shall
be liable to be forfeited by the Authority. The AR requests to grant
registration to the project subject to the submission of Environment clearance
& Fire scheme approval within 6 months, and mining permission before
commencement of construction and above DD/BG’s along with remaining
deficiencies before issuance of the certificate.
The
Authority has taken note of the submissions made by the Authorized
Representative of the promoter regarding the non-availability of the aforesaid
statutory approvals as on date. In view of the submission of proposal to submit
the Demand Draft / Bank Guarantee, amounting to Rs. 25,00,000/- each (Rupees
Twenty-Five Lakhs only) in lieu of timely submission of Environment clearance & Fire scheme approval, in favour of the
Authority, the promoter is directed to submit of following approvals:
A. Environment
clearance: within 6 months from the date of grant of registration; and
B. Fire scheme
approval: within 6 months from the date of grant of registration; and
C. Mining
permission: before commencement of construction
In
the event of non-submission of Environment clearance & Fire scheme approval
within the prescribed time frame, the corresponding security amount shall stand
forfeited by the Authority, and the failure to submit any of the above
approvals/ permissions within the prescribed timeframe may also attract
additional regulatory action as permissible under the Act of 2016, Rules and
Regulations made thereunder.
Approved
as proposed subject to rectification of deficiencies mentioned above.
The
Registration Certificate shall be issued after deposition of above BG/DDs and
rectification of other deficiencies as listed above at S. No. 36. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |