| 19-Jan-2026 |
Sh. Ashish Kush, Planning Executive and Sh. Ashish Dubey, Chartered
Accountant briefed about the facts of the case.
Sh. Arpit Goel, Sh. Navneet Kumar, Sh. Ravi kant Kumar and Sh. Virender
Singh Bansal are present on behalf of the promoter.
The Authorized Representative of the promoter submits that
presently, Revised Environment Clearance, Fire Scheme Approval, service plans and estimates and
Road access permission are under process and the said approvals have not yet
been obtained as on date. Further, the AR of the promoter undertakes to obtain and submit:
i.
The Revised Environment Clearance within 6 months from
the date of grant of registration.
ii.
The
Fire
Scheme Approval and Revised Service Plans and Estimates within 4 months from
the date of grant of registration.
iii. The Road access
permission within 2 months from the date of grant of registration.
He has submitted two
DD vide no. 516304
and 516305 dated 06.01.2026 amounting to Rs. 25 lakhs as a security amount for
submission of Fire Scheme Approval and Service plan and Estimates within 4
months from the grant of registration. Further, he undertakes to submit
the Demand Draft / Bank Guarantee amounting to Rs. 25 lakhs, as a security
deposit for timely compliance with the above requirements at point (i). It is
also expressly undertaken that in the event of failure to obtain and submit the
aforesaid approvals within the stipulated time frames, the said security
amount(s) shall be liable to be forfeited by the Authority.
The Authority has
taken note of the submissions made by the Authorized Representative of the
promoter regarding the non-availability of the aforesaid statutory approvals as
on date. In view of the above, and in the interest of regulatory compliance,
the Authority hereby directs that the promoter shall submit a separate Demand
Draft / Bank Guarantee, amounting to Rs. 25,00,000/- (Rupees Twenty-Five Lakhs
only), in favour of the Authority, as security amounts for timely submission of
the following approvals:
a. Revised Environment
Clearance within 6 months from the date of grant of registration.
In the event of
non-submission of any of the above approvals within the prescribed time frames,
the corresponding security amount shall stand forfeited by the Authority, and
such failure may also attract additional regulatory action as permissible under
the Act of 2016, rules and regulations made thereunder.
Approved as proposed subject to rectification of deficiencies mentioned
above.
The Registration Certificate shall be issued after submission of
remaining deficiencies mentioned above including correction in A-H form, Online
DPI and submission of the BG/DD of Rs. 25 lakhs for submission of Revised Environment Clearance
within the timeframe mentioned above. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |