| 01-Dec-2025 |
Ms. Deepika, Planning
Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of
the case.
Ms. Renu Basera (AR) and Sh.
Promod Agarwal (AR) are present on behalf of the promoter and stated that the
delay in completion of the project has occurred due to insufficient
applications received under the Affordable Housing Policy, which necessitated
repeated draws of allotment held on 19.12.2023, 22.02.2024, and 01.08.2024. It
was further stated that the remaining works are progressing at the site with
adequate pace to ensure timely completion of the project within the extended
timeline under Section 6 of the Act.
Approved as proposed,
subject to rectification of the deficiencies mentioned above.
The
Extension of Registration Certificate shall be issued after submission of
rectification of the remaining deficiencies, including corrections in the
Online DPI. |
EXTENSION APPROVED |