Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/1024/756/2025/127 DATED 22.12.2025 RERA-GRG-2068-2025 24-Sep-2025 22-Sep-2025 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Yes 08-Oct-2025 By hand By hand
First hearing View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/1024/756/2025/127 DATED 22.12.2025 01-Jan-2026 RC uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
15-Dec-2025 Proceedings dated: 15.12.2025.Sh. Shashank Sharma, Associate Engineer Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the case.Sh. Saurabh (AR), Ms. Pragya (AR) and Sh. Lakshmikant are present on behalf of the promoter.The Authorized Representative of the promoter submits that they have applied in the Authority for registration of additional license no. i.e., 13 of 2024 dated 29.01.2024 valid up to 28.01.2029 for residential plotted colony having land measuring 4.8284 acres and the registration of the said licensed land has been approved by the Authority today itself. The AR present states that, Environmental Clearance and Mining Permission are under process and the said approvals have not yet been obtained as on date. Further, the AR of the promoter undertakes to obtain and submit:         i.    The Approved Environmental Clearance within 6 months from the date of grant of registration; and        ii.    Mining permission before the start of construction.Further, he undertakes to submit a Demand Draft amounting to Rs. 25 lakhs, as a security deposit for timely compliance with the above requirement at point (i). It is also expressly undertaken that in the event of failure to obtain and submit the aforesaid approval within the stipulated time frames, the said security amount shall be liable to be forfeited by the Authority.The Authority has noted that promoter has applied for registration of additional license number i.e., 13 of 2024 dated 29.01.2024 valid up to 28.01.2029 for residential plotted colony having land measuring 4.8284 acres on 17.11.2025 in the Authority, which was unregistered land initially and after due compliance, said licensed land has been registered in the agenda of today’s meeting itself i.e., 15.12.2025.Further, the Authority has taken note of the submissions made by the Authorized Representative of the promoter regarding the non-availability of the aforesaid statutory approvals as on date. In view of the above, and in the interest of regulatory compliance, the Authority hereby directs that the promoter shall submit a Demand Draft amounting to Rs. 25,00,000/- (Rupees Twenty-Five Lakhs only), in favour of the Authority, as security amount for timely submission of approved Environmental Clearance within 6 months from the date of grant of registration.In the event of non-submission of the above approval within the prescribed time frames, the said security amount shall stand forfeited by the Authority, and such failure may also attract additional regulatory action as permissible under the Act of 2016, rules and regulations made thereunder. Further, the promoter shall submit Mining permission before start of construction.Approved as proposed subject to rectification of deficiencies mentioned above.The Registration Certificate shall be issued after submission of remaining deficiencies mentioned above including correction in A-H form, Online DPI and submission of a DD of Rs. 25 lakhs for submission of Approved Environmental Clearance within the timeframe mentioned above.  APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS View Order
24-Nov-2025 The matter has been adjourned to 15.12.2025 ADJOURNMENT View Order
03-Nov-2025 The matter has been adjourned to 24.11.2025 ADJOURNMENT View Order
13-Oct-2025 Proceedings dated: 13.10.2025. Sh. Shashank Sharma, Associate Engineer Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the case. Sh. Saurabh (AR), Sh. Lakshmikant and Ms. Pragya (AR) are present on behalf of the promoter and states that license no 13 of 2024 dated 29.01.2024 valid up to 28.01.2029 has been granted by DTCP in favour of M/s MLT Propmart Pvt. Ltd. in collaboration with M/s St. Patricks Realty Pvt. Ltd and the building plans has been passed by DTCP vide memo no ZP-1143/JD(RA)/2025/29230 dated 30.07.2025 valid up to 29.07.2030 for the development of commercial complex. The Authorized Representatives of the promoter further submits that addendum to the previous collaboration agreement has been done and clause regarding irrevocability has been incorporated in the same. The reply to the remaining deficiencies will be submitted within a period of one week. The Authority observes that the promoter submitted an application dated 24.09.2025 under Section 4 of the Real Estate (Regulation and Development) Act, 2016 in the Authority for the registration of distinct commercial component. The registration application under consideration pertains to license no. i.e., 13 of 2024 dated 29.01.2024 valid up to 28.01.2029 for land measuring 4.8284 acres issued in favour of M/s MLT Propmart Pvt. Ltd. in collaboration with M/s St. Patricks Realty Pvt. Ltd. for the development of residential plotted colony in addition to the license no 54 of 2014 dated 20.06.2014, 28 of 2016 dated 23.12.2016, 07 of 2020 dated 29.01.2020 and 104 of 2021 dated 10.12.2021 situated in Sector – 29, 30, 32, & 33, Sohna, Gurugram. Further, the licensed area i.e., 4.8284 acres for development of the residential plotted colony under license No. 13 of 2024 dated 29.01.2024 has not yet been registered with the Authority and the promoter has sought the registration of distinct commercial component for an area admeasuring 3.419 acres, which form part of the aforesaid licensed land for which building plans has been passed by DTCP dated 30.07.2025. Keeping in view of the aforesaid facts, and submissions made by the Authorized Representative of the promoter, Authority hereby directs the promoter to get the additional license i.e., 13 of 2024 dated 29.01.2024 registered with the Authority first and thereafter distinct commercial component on the said licensed land can be registered. Further promoter is directed to submit the remaining deficiencies in the Authority. The matter to come up on 03.11.2025. EXAMINATION BY AUTHORITY View Order