| 13-Oct-2025 |
Ms. Deepika, Planning
Executive and Ms. Asha, Chartered Accountant briefed about the facts of the
project.
Sh. Saurabh Bhardwaj (AR) & Ms. Pragya (AR) are present on behalf of the promoter.
The Authorized Representative
of the promoter submits that presently, the environment clearance and mining permission are under process and the said
approvals have not yet been obtained as on date. Further, the AR of the promoter undertakes to obtain and submit:
i.
The approved environmental clearance within 3 months from the date of
grant of registration.
ii. Mining permission before the
start of construction.
Further, he undertakes to
submit Demand Drafts / Bank Guarantees amounting to Rs 25 lakhs, as a security
deposit for timely compliance with the above requirements at point (i). It is
also expressly undertaken that in the event of failure to obtain and submit the
aforesaid approval within the stipulated time frame, the said security amount
shall be liable to be forfeited by the Authority.
The Authority has taken note
of the submissions made by the Authorized Representative of the promoter
regarding the non-availability of the aforesaid statutory approvals as on date.
In view of the above, and in the interest of regulatory compliance, the Authority
hereby directs that the promoter shall submit the Demand Drafts / Bank
Guarantee, amounting to Rs. 25,00,000/- (Rupees Twenty-Five Lakhs only), in
favour of the Authority, as security amount for timely submission of the
approved environmental clearance within 3 months from the date of grant of
registration;
In the event of non-submission
of any of the above approval within the prescribed time frame, the
corresponding security amount shall stand forfeited by the Authority, and such
failure may also attract additional regulatory action as permissible under the
Act of 2016, rules and regulations made thereunder. Further, the promoter shall
also submit the mining permission before the start of construction.
Approved
as proposed subject to rectification of deficiencies mentioned above.
The
Registration Certificate shall be issued after submission of remaining
deficiencies mentioned above including correction in A-H form, Online DPI and
submission of BG/DD of Rs. 25 lakhs for submission of approved environment clearance within the timeframe
mentioned above. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |