| 13-Oct-2025 |
Sh. Ashish Kush, Planning Executive and Ms. Asha, Chartered Accountant
briefed about the facts of the case.
Sh. Vineet Maheshwari, Sh. Siddhartha Kapoor and Sh. Vedant Batra are
present on behalf of the promoter.
The AR of the promoter states that near about 80% of the construction
have been completed and the remaining works are
progressing at site with pace to ensure timely completion of the project within
extended timeline u/s 6. Further, states that the site is accessible from 24
m wide road which is already constructed.
Approved as proposed, subject to rectification of the deficiencies
mentioned above.
The Extension of Registration Certificate shall be issued after submission
of rectification of remaining deficiencies including corrections in Online DPI. |
EXTENSION APPROVED |