| 08-Dec-2025 |
Ms.
Nikita Mittal, Planning Executive and Ms. Asha, Chartered Accountant briefed
about the facts of the project.
Sh.
Piyush Jain (Managing Partner), Sh. Manoj Kumar (CEO), Sh. Rounak Kumar Bansal
(VP) are present on the behalf of the promoter. Smt. Sudesh is present on the
behalf of the landowner.
The
AR of the promoter states that few documents were filed with the Authority on
the previous Friday i.e., 05.12.2025. The concerned official is directed to
examine the said documents.
The
AR of promoter states that the site is accessible through existing 5-karam-wide
road, which will be widened to a 24-meter road as per the approved development
plan and they will construct the part of the 24-meter road that falls on their
land at its own cost and other promoters will also construct their portions
falling on their respective lands. Further, the promoter will gift the land on
which the said 24-meter road is to be constructed to the Government through a
Gift Deed for the affordable group housing project (8.84375 acres, License No.
73 of 2025 dated 22.05.2025, Farrukhnagar, Sector-3, Gurgaon). Accordingly, the
authority directs the promoter to submit an undertaking regarding the same.
Further, the AR of the promoter states that HT line is passing through the
project site and ROW has been maintained and further measures will be taken to
shift the HT line underground with the concerned department. Meanwhile, the
promoter is directed to disclose these details (recent road access and HT line)
in the advertisement and brochure, and the same conditions shall be
incorporated into the registration certificate.The
Authorized Representative of the promoter submits that presently, the
Environment clearance, Fire Scheme Approval and Approved service plans and
estimates are under process and the said approvals have not yet been obtained
as on date. Further, the AR of the promoter undertakes to obtain and submit:i. The Approved Environmental Clearance within
6 months from the date of grant of registration, andii. The Fire Scheme Approval and Approved Service
Plans and Estimates within 4 months from the date of grant of registration.Further,
he undertakes to submit three Demand Drafts / Bank Guarantees amounting to Rs.
25 lakhs each, as a security deposit for timely compliance with the above
requirements. It is also expressly undertaken that in the event of failure to
obtain and submit the aforesaid approvals within the stipulated time frames,
the said security amount(s) shall be liable to be forfeited by the Authority.The
Authority has taken note of the submissions made by the Authorized
Representative of the promoter regarding the non-availability of the aforesaid
statutory approvals as on date. In view of the above, and in the interest of
regulatory compliance, the Authority hereby directs that the promoter shall
submit three separate Demand Drafts / Bank Guarantees, each amounting to Rs.
25,00,000/- (Rupees Twenty-Five Lakhs only), in favour of the Authority, as
security amounts for timely submission of the following approvals:a. Environmental Clearance: within 6 months
from the date of grant of registration;b. Fire Scheme Approval: within 4 months from
the date of grant of registration; and c. Approved Service Plans and Estimates:
within 4 months from the date of grant of registration.In
the event of non-submission of any of the above approvals within the prescribed
time frames, the corresponding security amount shall stand forfeited by the
Authority, and such failure may also attract additional regulatory action as
permissible under the Act of 2016, rules and regulations made thereunder. Approved
as proposed subject to rectification of deficiencies mentioned above at Sr. No.
30.
The
Registration Certificate shall be issued after submission of remaining
deficiencies mentioned above at Sr. No. 30 including corrections in A-H form,
Online DPI and submission of three BG/DD of Rs. 25 lakhs each for submission of
Approved Environment Clearance, Fire Scheme approval and approved Service plan
and Estimates within the timeframe mentioned above. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |