| 27-Apr-2026 |
Ms. Deepika, Planning
Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of
the project.
Sh. Karan Sharma (Director),
Sh. Rajesh Kumar (AR), Sh. Ashish Varghese (AR) are present on behalf of
promoter.
The Director of the promoter company
submits that the land applied for registration u/s 4 of the Act, 2016 is free
from any kind of litigation. Accordingly, an affidavit from the Managing
Director to this effect is also being submitted. At present, the fire Scheme
approval, approved service plans and estimates, approved electrification plan,
and storm water drainage assurance are under process, and the said approvals
have not yet been obtained as of date. Further, the Authorized Representative
of the promoter undertakes to obtain and submit:
i.
Fire
Scheme approval & approved service plans and estimates within 6 months from
the date of grant of registration; and
ii.
Approved
Electrification plan within 6 months from the date of grant of registration;
Further, he undertakes to
submit the two Demand Drafts amounting to Rs. 25 lakhs each, as a security
deposit for timely compliance with the above requirements at point (i). It is
also expressly undertaken that in the event of failure to obtain and submit the
aforesaid approval within the stipulated time frames, the said security amount
shall be liable to be forfeited by the Authority.
The Authority has taken note
of the submissions made by the Director of the promoter regarding the
non-availability of the aforesaid statutory approvals as on date. In view of
the above, and in the interest of regulatory compliance, the Authority hereby
directs that the promoter shall submit the two Demand Drafts amounting to Rs.
25,00,000/- (Rupees Twenty-Five Lakhs only) each, in favour of the Authority as
security amounts for timely submission of fire scheme approval and approved
service plans and estimates within 6 months from the date of grant of
registration.
In the event of
non-submission of the above approvals within the prescribed time frames, the
corresponding security amount shall stand forfeited by the Authority, and such
failure may also attract additional regulatory action as permissible under the
Act of 2016, rules and regulations made thereunder. Further, the promoter shall
submit approved electrification plan within 6 months from the date of grant of
registration.
Approved as proposed subject
to rectification of deficiencies mentioned above.
The Registration Certificate shall be issued after
submission of the remaining deficiencies mentioned above including correction
in Form A–H, online DPI and submission of two Demand Drafts of Rs. 25,00,000/-
(Rupees Twenty-Five Lakhs only) each for submission of fire scheme approval and
approved service plans and estimates within the time frame mentioned above,
along with the deficiency mentioned at S. No. 33. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |