| 15-Sep-2025 |
Ar.
Neeraj Gautam, Associate Architectural Executive and Sh. Ashish Dubey,
Chartered Accountant briefed about the facts of the project.
Sh.
Anoop Sharma (AR) and Sh. Satyendra Tiwari, AR and Satinder Singh, Assistant
Manager are present on behalf of the promoter and states that as per the
directions of the Authority in the hearing dated 01.09.2025, the promoter has
submitted the attachment orders of ED, Supreme court orders dated 11.01.2023
and 19.05.2022, copy of the report of Hon’ble Justice Geeta Mittal, color coded
maps showing the areas attached by ED and allocation of area between Brahma
City Pvt. Ltd and Krrish Realtech Pvt. Ltd. and affidavit through director
declaring that the area falling under development of M/s Brahma City Pvt. Ltd.
has not been attached by ED and that as on date, no area/ piece of land falling
under the development of M/s Brahma City Pvt. Ltd. has been attached, frozen or
otherwise restricted by any agency, court, department.
In
case any part of land falling under the development of M/s Brahma City Pvt.
Ltd. is found to be attached by the Enforcement Directorate or any adverse
order with respect to the subject land is passed by the Enforcement
Directorate, the order of Enforcement Directorate shall prevail. Further, if
any submissions/ declarations/undertakings submitted by the promoter are found
to be false or misleading, the promoter shall be liable for legal proceedings as
well.
The
AR further states that the development of the project pertaining to
current application is completed in all aspects. However, the land being part
of the total licensed area measuring 141.66875 acres, the DTCP will issue the
completion certificate for the entire licensed area and all the infrastructure
and services including roads, water supply, sewerage, drainage, etc.
With
respect to the revalidation of environmental clearance, the AR states that the
revalidation of environmental clearance could not be obtained due to the delay
in constitution of SEIAA/SEAC. The process for handling proposals pending
before SEIAA were transferred to Central Level, EAC, for processing and
approval. The stay granted by the Hon’ble Supreme Court in WPC 166/2025 Van
Shakti V/s Union of India has been vacated on 05.08.2025 and a new committee has
now been formed and is functional. The AR states that revalidated environmental
clearance of the project shall be submitted within 4 months of issuance of the
certificate.
The
Authority observes that the DTCP has renewed the license of the project on
request of M/s Brahma City Pvt. Ltd. considering the fact that there is no
attachment of land or pending litigation in the area falling under the
development of M/s Brahma City Pvt. Ltd. and the said license is now valid up
to 20.08.2030.
In
view of the above, the extension of the registration certificate is approved as
proposed subject to the submission of revalidated environmental clearance of
the project within 4 months and rectification of remaining deficiencies listed
above at S. No. 33. The promoter is directed to abide by the directions of
Hon’ble Supreme Court/ Hon'ble High Court in SLP No. 6013 of 2022 and CWP
No. 2926 of 2022.
Since
CWP No. 2926 of 2022 is still pending before Hon'ble Punjab and Haryana High
Court, the extension of the registration certificate is approved without
prejudice to the matter pending before the Hon'ble Punjab and Haryana High
Court in CWP No. 2926 of 2022. It shall also be construed to be amended with
respect to any variations as may be passed by the Hon'ble High Court in the
above-said matter. This is without prejudice to the rights of the allottees of
the project under Section 14 & 18 of the Act of 2016. The
above is only an extension of registration already granted with existing
allottees to enable the completion of the project and not a fresh registration.
The
certificate shall be issued after rectification of the above deficiencies by
the promoter. |
EXTENSION APPROVED |
View Order |
| 18-Aug-2025 |
Ar.
Neeraj Gautam, Associate Architectural Executive and Sh. Ashish Dubey,
Chartered Accountant briefed about the facts of the project.
Sh.
Anoop Sharma (AR), Sh. Satyendra Tiwari (AR) and Sh. Satinder Singh (AR) are
present on behalf of the promoter and states that they have already obtained
the renewal of license and environmental clearance of the project. The AR
further states that the development of the project pertaining to current
application is completed in all aspects. However, the land being part of the
total licensed area measuring 141.66875 acres, the DTCP will issue the
completion certificate for the entire licensed area. Some portion of the
license which comes under other developer i.e., M/s Krrish Realtech Pvt. Ltd.
is under litigation. However, the area falling under the present application is
litigation free and the same is confirmed in the report of Hon’ble Justice
Geeta Mittal who was appointed as Special Referee by Hon’ble Supreme Court to
look into the claims and counter claims of respective parties, in respect of
plots purchased/ agreed to be purchased by the parties. Further, a portion of
the project land belonging to M/s Krrish Realtech Pvt. Ltd. has been attached
by the Enforcement Directorate vide orders dated 06.08.2024 and 17.10.2024
under the provisions of Prevention of Money Laundering Act, 2002. It is
clarified that no project land falling in the allocation of M/s Brahma City
Pvt. Ltd. has been attached and the same is confirmed in the attachment order
of the Enforcement Directorate. Further, the DTCP vide its rectification order
dated 06.12.2022 has removed the restriction on creation of 3rd party
rights in respect of commercial and community sites of the project land and a
copy of same will be submitted to the Authority.
In
view of the above, the promoter is directed to submit the undertaking with
respect to no litigation on the area falling under current application through
a duly authorized signatory along with the copies of report of Hon’ble Justice
Geeta Mittal, attachment order of the Enforcement Directorate, the allocation
of M/s Brahma City Pvt. Ltd. and the area attached by ED duly marked on the
layout plan as well as the rectification order of DTCP dated 06.12.2022. The
promoter is further directed to submit the copy of renewal of license and
environmental clearance in the Authority along with the other remaining
deficiencies.
The
matter to come up on 01.09.2025. |
ADJOURNMENT |
View Order |