| 29-Sep-2025 |
Ar. Neeraj Gautam, Associate Architectural
Executive and Ms. Asha, Chartered Accountant briefed about the facts of the
project.
Sh. Harish Yadav (AR) and Sh. Ami Kumar (AR) appeared
on behalf of the promoter.
Sh. Gopal Krishan Yadav, Smt. Tara and Sh.
Shri Niwas appeared on behalf of the landowners.
The site of the project was visited by the
concerned executive and it is noted that presently, the site is accessible
through 6 Karam wide Pataudi- Khor road and the proposed 24 m wide road is yet
to be developed.
The Authorized Representative
of the promoter submits that presently, the road access permission and Approved
service plans and estimates are under process and the said approvals
have not yet been obtained as on date. Further, the AR of
the promoter undertakes to obtain and submit the same within 4 months from the
date of issuance of registration certificate. He further undertakes to submit two
Demand Drafts / Bank Guarantees amounting to Rs. 25 lakhs each, as a security
deposit for timely compliance with the above requirements. It is also expressly
undertaken that in the event of failure to obtain and submit the aforesaid
approvals within the stipulated time frames, the said security amount(s) shall
be liable to be forfeited by the Authority.
The Authority has taken note of the submissions made
by the Authorized Representative of the promoter regarding the non-availability
of the aforesaid statutory approvals as on date. In view of the above, and in
the interest of regulatory compliance, the Authority hereby directs that the
promoter shall submit two separate Demand Drafts / Bank Guarantees, each
amounting to Rs. 25,00,000/- (Rupees Twenty-Five Lakhs only), in favour of the
Authority, as security amounts for timely submission of the following approvals:
a. Road access
permission: within 4 months from the date of issuance of registration; and
b. Approved Service
Plans and Estimates: within 4 months from the date of issuance of registration.
In the event of non-submission
of any of the above approvals within the prescribed time frames, the
corresponding security amount shall stand forfeited by the Authority, and such
failure may also attract additional regulatory action as permissible under the Act
of 2016, rules and regulations made thereunder.
The registration of the project is approved as
proposed subject to rectification of form REP-I and DPI; submission of approved
service plans & estimates and road access permission within 4 months of
issuance of registration certificate. Further, a declaration regarding existing
access to the site from 6 Karam wide revenue road shall be part of the
advertisement and brochure.
The registration certificate shall be issued with
the condition to be mentioned in the registration certificate regarding
declaration of existing accessibility of the site and after the rectification/
submission of the above documents and submission
of three BG/DD of Rs. 25 lakhs each for submission of approved service plans
& estimates and road access permission within the timeframe mentioned above. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |