21-Jul-2025 |
Proceedings
dated 21.07.2025.
Sh.
Shashank Sharma, Associate
Engineer Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the
facts of the case.
Sh. Vipul Dahiya (AR) is present
on behalf of the promoter and states that Original CA certifcate of expenditure
incurred and to be incurred is being submitted today and Original NOC’s from
both the lenders will be submitted within 2 days in the Authority.
Meanwhile, the site of the
project was visited physically on 10.07.2025 by the concerned Associate
Engineer Executive along with Chartered Accountant and it has been noted that
the project namely “JMS Group The Majestic Floors” is a part of the project
“The Golden City” which is well connected to the 60 mtr wide sector road and
the services such as water supply, sewer line, electrical and storm line has
been laid down.
Approved as proposed. The RC
shall be issued after submission of corrections in form A-H, DPI and other
remaining documents. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |