| 08-Dec-2025 |
Ar.
Neeraj Gautam, Associate Architectural Executive and Sh. Ashish Dubey,
Chartered Accountant briefed about the facts of the project.
Sh.
Sunil Kumar (AR), Sh. Deepak Lohia (AR) and Sh. Naresh Bisht (AR) are appeared
on behalf of the promoter.
Th
AR of the promoter requests the Authority to approve the extension of the
registration of the project and assures that the rectified documents will be
submitted to the Authority before the issuance of the certificate.
The
site of the project was visited and it was noted that the structure of all 6
residential towers is completed and the finishing works including painting of
inner and outer walls, tiling of floors and fixing of railings has commenced.
The community center and commercial block is under construction. The sewage
treatment plant has been installed. Laying of internal services is yet to
commence.
Upon
the perusal of the forensic audit report dated 27.10.2025 submitted by M/s Adroit & Co., it
is noted that there is a misappropriation of Rs. 30.85 crores in the project
account. Since the application pertains to an affordable group housing project,
and accordingly the DTCP, Haryana be intimated about the misappropriation of funds by the promoter
along with a copy of forensic audit report for their information and necessary
action as desired.
The
AR of the promoter states that the delay in completion of the project is
primarily due to COVID pandemic and NGT restrictions over construction.
However, the work on site is now in full swing and the project is nearing
completion. The AR further assures that the units will be handed over within
the time period sought in the extension application.
The
Authority decides to grant extension of the registration of the project subject
to the rectification of the deficiencies listed above at S. No. 42.
The
certificate shall be issued after the submission of deficiencies listed above
at S. No. 42. |
EXTENSION APPROVED |
View Order |
| 24-Nov-2025 |
THE MATTER TO COME UP ON 08.12.2025 |
ADJOURNMENT |
View Order |
| 27-Oct-2025 |
THE MATTER TO COME UP ON 24.11.2025 |
ADJOURNMENT |
View Order |
| 29-Sep-2025 |
THE MATTER TO COME UP ON 27.10.2025 |
ADJOURNMENT |
View Order |
| 08-Sep-2025 |
Ar.
Neeraj Gautam, Associate Architectural Executive and Sh. Ashish Dubey,
Chartered Accountant briefed about the facts of the project.
None
appeared on behalf of the promoter. M/s Adroit & Co. is appointed to carry out the
forensic audit of the project vide letter dated 27.08.2025. The forensic
auditor’s report is to be submitted by 25.09.2025. Meanwhile, the promoter is
directed to rectify the remaining
deficiencies conveyed vide notice dated 09.07.2025. Further, the promoter is
again directed to submit the data to forensic auditor with a copy to the
Authority.
The
matter to come up on 29.09.2025. |
ADJOURNMENT |
View Order |
| 18-Aug-2025 |
Ar.
Neeraj Gautam, Associate Architectural Executive and Sh. Ashish Dubey,
Chartered Accountant briefed about the facts of the project.
Sh.
Naresh Bisht (AR) is present on behalf of the promoter and requested for three
weeks’ time to submit the remaining deficiencies in the Authority.
It
is noted that the promoter has collected a total of Rs. 158.03 Crores from the
allottees of the project and has spent Rs. 107.59 Crores so far against the
total project cost of Rs. 144.39 Crores as per the details provided by the
promoter under quarterly progress report of the project. The amount collected
from the allottees so far does not seem commensurate with the development on
the site. In view of the fact that the project is an Affordable Group Housing,
the Authority decides that a forensic auditor be appointed to conduct the
forensic audit of the project and promoter shall submit the data to forensic
auditor with a copy to the Authority within a period of one week after the
appointment of the same and cost of the forensic audit is to be borne by the
promoter.
The
AR of the promoter is directed to submit the remaining deficiencies including
the deficit fee in the Authority before the next date of hearing.
The
matter to come up on 08.09.2025 |
ADJOURNMENT |
View Order |
| 21-Jul-2025 |
THE MATTER TO COME UP ON 18.08.2025 |
ADJOURNMENT |
View Order |
| 07-Jul-2025 |
THE MATTER TO COME UP ON 21.07.2025 |
EXAMINATION BY AUTHORITY |
View Order |