| 29-Sep-2025 |
Ms. Deepika,
Planning Executive and Ms. Asha, Chartered Accountant briefed about the facts
of the case.
Sh.
Ashish Drall (AR) & Sh. Pankaj Sharma (Advocate) are present on behalf of
the promoter and states that the application for approval of service plans and
estimates, fire scheme approval, environment clearence and road access
permission have been applied in the competent authorities and the said
approvals have not yet been obtained as on date. Further, the AR of the promoter undertakes to obtain and
submit:
i.
The Approved Environmental Clearance within 6 months
from the date of grant of registration, and
ii. The Fire Scheme
Approval, road access permission and Approved Service Plans and Estimates
within 4 months from the date of grant of registration.
Further, he
undertakes to submit three Demand Drafts / Bank Guarantees amounting to Rs. 25
lakhs each, as a security deposit for timely compliance with the above
requirements. It is also expressly undertaken that in the event of failure to
obtain and submit the aforesaid approvals within the stipulated time frames,
the said security amount(s) shall be liable to be forfeited by the Authority.
The Authority has
taken note of the submissions made by the AR of the promoter regarding the
non-availability of the aforesaid statutory approvals as on date. In view of
the above, and in the interest of regulatory compliance, the Authority hereby
directs that the promoter shall submit three separate Demand Drafts / Bank
Guarantees, each amounting to Rs. 25,00,000/- (Rupees Twenty-Five Lakhs only),
in favour of the Authority, as security amounts for timely submission of the
following approvals:
a. Environmental
Clearance: within 6 months from the date of grant of registration;
b. Fire Scheme Approval:
within 4 months from the date of grant of registration; and
c. Approved Service
Plans and Estimates: within 4 months from the date of grant of registration.
In the event of
non-submission of any of the above approvals within the prescribed time frames,
the corresponding security amount shall stand forfeited by the Authority, and
such failure may also attract additional regulatory action as permissible under
the Act of 2016, rules and regulations made thereunder.
Approved as
proposed subject to rectification of deficiencies mentioned above.
The Registration
Certificate shall be issued after submission of remaining deficiencies
mentioned above including correction in A-H form, Online DPI and submission of
three BG/DD of Rs. 25 lakhs each for submission of approved Environment
Clearance, Fire Scheme approval and approved Service plan and Estimates within
the timeframe mentioned above. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |