21-Apr-2025 |
Sh. Ashish
Kush, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed
about the facts of the case.
Sh. Vineet Maheshwari (President), Sh. Siddhartha Kapoor (AVP) and Sh.
Ravindra (AR) are present on behalf of the promoter.
The promoter shall submit a BG/DD of Rs 25 lakhs as a security amount for
submission of Approved service plan and estimates within 4 months from the date
of grant of registration.
Approved as proposed subject to rectification of deficiencies mentioned
above and submission of BG/DD of Rs 25 lakhs for submission of Approved service
plan and estimates within 4 months from the date of grant of registration.
The Registration Certificate shall be issued after submission of
remaining deficiencies mentioned above including correction in A-H form, Online
DPI and submission of BG/DD of Rs 25 lakhs. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
24-Mar-2025 |
Sh.
Ashish Kush, Planning
Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of
the case.
Sh.
Vineet Maheshwari (President), Sh. Siddhartha Kapoor (AVP) and Sh. Vedant Batra
(CS) are present on behalf of the promoter.
The
AR of the promoter stated that no sale, booking, advertisement has been made on
the basis of building plans approved for S+3 floors.
A
public notice of two weeks for inviting objections from the
allottees be issued in at least three prominent newspapers (Two English and One
Hindi) of wide circulation regarding the revision in the earlier approved
building plan from S+3 floors to S+4 floors. Further, the promoter is directed
to remove the above mentioned deficiencies.
The
matter to come up on 21.04.2025. |
ADJOURNMENT |
View Order |
10-Mar-2025 |
The matter is adjourned and to come up on 24.03.2025. |
EXAMINATION BY AUTHORITY |
View Order |