| 21-Apr-2025 |
Sh. Prachi Singh, planning Executive briefed about the facts of the case.
Sh. Vineet Maheshwari (President), Sh. Siddhartha Kapoor (AV) and Sh. Ravindra (AR) are present on
behalf of the promoter.
one year.
The promoter requests to make an amendment in the registered plot number from 38 to 36 due to
revision in Iayout plan and issue an amended registration certificate and further grant the extension of consequently, the promoter is directed to submit a separate application along with supporting
documents for the amendment of registration certificate.in view of the above, the extension requested u/s 6 of Act of 2016 is approved as Proposed. The RC shall be issued after the above compliances are made. |
EXTENSION APPROVED |
View Order |
| 24-Mar-2025 |
Sh.
Prachi Singh,
Planning Executive briefed about the facts of the case.
Sh.
Vineet Maheshwari (President), Sh. Siddhartha Kapoor (AVP) and Sh. Vedant Batra
(CS) are present on behalf of the promoter.
A
public notice of two weeks for inviting objections from
the allottees be issued in at least three prominent newspapers (Two English and
One Hindi) of wide circulation regarding revision in the earlier
approved layout plan which got revised due to grant of the additional license.
Further, the promoter is directed to remove the above mentioned deficiencies.
The
matter to come up on 21.04.2025. |
ADJOURNMENT |
--- |
| 10-Mar-2025 |
Ms. Prachi Singh, Planning Executive briefed about
the facts of the project.
Sh. Vineet Maheshwari (President), Sh. Siddhartha
Kapoor (AV) and Sh. Vedant Batra (AR) are present on behalf of the promoter and
states that there is a revision of layout plan due to additional license area admeasuring
2.96875 acres. Further, the total number of plots are reduced from 38 to 36 as
2 plots are omitted because of proposed 9 mtrs. internal road for better
connectivity. The promoter requests to amend the registration certificate for
36 plots and accordingly grant the extension of the registration of project.
The authority directs the concerned official to verify
the facts submitted by the promoter. Meanwhile, the promoter is directed to
remove the remaining deficiencies.
The matter to come up on 24.03.2025. |
ADJOURNMENT |
--- |
| 11-Feb-2025 |
The matter is adjourned and to come up on 10.03.2025. |
ADJOURNMENT |
--- |
| 10-Feb-2025 |
The matter is adjourned and to come up on 11.02.2025 at 03:00 PM. |
ADJOURNMENT |
--- |
| 20-Jan-2025 |
The matter is adjourned and to come up on 10.02.2025. |