| 11-Feb-2025 |
Sh. Ashish Kush,
Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the
facts of the case.
Ms. Julie Jha (AR)
and Sh. Vijay Singh (AR) are present on behalf of the promoter.
No objection has been received in
the Authority from any allottee in respect of public notice dated 23.01.2025
regarding revision in
the building plans.
Approved as proposed
subject to rectification of deficiencies mentioned above including correction
in A-H form and Online DPI.
The promoter shall
submit two BG/DD amounting to Rs. 25 lakhs each as security amount for
submission of Revised Fire Scheme approval and Revised Service Plans and
Estimates within a period of four months.
The addendum
Certificate shall be issued after submission of remaining deficiencies
mentioned above including correction in A-H form, Online DPI and submission of
BG/DD of Rs 25 lakhs each for submission of Revised Fire Scheme approval and
Revised Service Plans and Estimates. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
| 05-Feb-2025 |
Sh. Ashish Kush, Planning
Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of
the case.
Ms. Julie Jha (AR), Sh. Vijay
Singh (AR) are present on behalf of the promoter
The promoter has
submitted the consents of more than two-third existing allottees in the
project. Accordingly, a public notice was published in three newspapers i.e., The
Times of India (English), The Tribune (English) and NBT Nav Bharat Times
(Hindi) dated 23.01.2025 for inviting objections till 01.02.2025 regarding
revision in the building plans of the project.
No
objections have been received in the Authority against the same and none
appeared before the Authority today.
The concerned
official of the Authority is directed to convey the deficiencies, if any in the
application.
The matter is
adjourned and to come up on 11.02.2025 at 3 pm. |
ADJOURNMENT |
View Order |
| 20-Jan-2025 |
Sh. Ashish Kush, Planning
Executive and Ms. Asha, Chartered Accountant briefed about the facts of the
case.
Ms. Julie Jha (AR), Sh. Vijay
Singh (AR) are present on behalf of the promoter.
The AR of the
promoter states that the building plans have been revised on 10.12.2024 and
they have submitted the consent of 208 unique allottees out of 284 unique
allottees out of total 317 sold units regarding the revision in building plans.
The
Authority decides to issue a public notice of 10 days for inviting objections
from the allottees in atleast three prominent newspapers (Two English and One
Hindi) of wide circulation regarding revision in the building plans.
Further, the office
to randomly verify the consents submitted by the promoter.
The matter to come
up on 05.02.2025 at 3 pm. |
ADJOURNMENT |
View Order |
| 06-Jan-2025 |
Due to gazetted holiday, the matter is adjourned and to come up on 20.01.2025. |
EXAMINATION BY AUTHORITY |
View Order |