| Project Name | Project Location | Project District | Project Tehsil | Promoter Name |
|---|---|---|---|---|
| Commercial colony | Sector-92, mewka, gurugram | GURUGRAM | Ameya commercials projects pvt. ltd |
| Project Id | Receiving Date | Online Submission Date | Current Status | Next Date of Hearing | Notice Dispatched | Notice Dispatched On | Notice Tracking Id | Notice Dispatched Remarks | View Notice | Initially Scrutinized Remarks |
|---|---|---|---|---|---|---|---|---|---|---|
| RERA-GRG-1818-2024 | 04-Dec-2024 | 04-Dec-2024 | EXTENSION APPROVED | NOT REQUIRED | Yes | 13-Dec-2024 | BY MAIL | FIRST DEFICIENCY NOTICE | First hearing |
| Date of Hearing | Proceedings of the day | Status | Order |
|---|---|---|---|
| 09-Jun-2025 | EXTENSION APPROVED | View Order | |
| 26-May-2025 | The matter is adjourned and to come up on 09.06.2025. | ADJOURNMENT | View Order |
| 21-Apr-2025 | Sh. Ashish Kush, Planning Executive and Ms. Asha, Chartered Accountant briefed about the facts of the case. Sh. Akshat Gupta (AR) and Sh. Sanjeev Gupta (AR) are present on behalf of the promoter. The AR of the promoter stated that they have obtained the revalidation of building plans and in process of obtaining the remaining approval which are in process and expected to obtain within one month. In view of the same, the AR of the promoter seeks four weeks’ time to rectify the above mentioned deficiencies. Meanwhile, the PE/PC to visit the site of the project. In view of the same, the request is allowed and the matter to come up on 26.05.2025. | ADJOURNMENT | View Order |
| 24-Mar-2025 | The matter is adjourned and to come up on 21.04.2025. | ADJOURNMENT | View Order |
| 27-Jan-2025 | The matter is adjourned and to come up on 24.03.2025. | ADJOURNMENT | View Order |
| 23-Dec-2024 | The matter is adjourned and to come up on 27.01.2025. | EXAMINATION BY AUTHORITY | View Order |