Project Name | Project Location | Project District | Project Tehsil | Promoter Name |
---|---|---|---|---|
MRG Crown | Village Babupur, Sector 106, | GURUGRAM | Gurgaon | MRG Group India Private Limited |
Project Registration Number | Project Id | Receiving Date | Online Submission Date | Current Status | Next Date of Hearing | Notice Dispatched | Notice Dispatched On | Notice Tracking Id | Notice Dispatched Remarks | View Notice | Initially Scrutinized Remarks | Details of Project(Form A-H) |
---|---|---|---|---|---|---|---|---|---|---|---|---|
GGM/937/669/2025/40 DATED 16.04.2025 | RERA-GRG-1816-2024 | 18-Dec-2024 | 18-Dec-2024 | APPROVED AND CERTIFICATE UPLOADED | NOT REQUIRED | Not Yet | -- | First hearing | View Form(A-H) |
Project Registration Number | Uploading Date | Remarks | View Certificate |
---|---|---|---|
GGM/937/669/2025/40 DATED 16.04.2025 | 21-May-2025 | RC Uploaded |
Date of Hearing | Proceedings of the day | Status | Order |
---|---|---|---|
24-Feb-2025 | Ms. Nikita Mittal, Planning Executive and Ms. Asha, Chartered Accountant briefed about the facts of the case. Ms. Anjana Gulati (AR) is present on behalf of the promoter. Approved as proposed subject to rectification of deficiencies as pointed out at S. No. 24 above. The registration certificate shall be issued after removal of remaining deficiencies. | APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS | View Order |
17-Feb-2025 | The matter is adjourned and to come up on 24.02.2025. | ADJOURNMENT | --- |
27-Jan-2025 | The matter is adjourned and to come up on 17.02.2025. | ADJOURNMENT | --- |
13-Jan-2025 | The matter is adjourned and to come up on 27.01.2025. | EXAMINATION BY AUTHORITY | --- |