Comprehensive Project Details
Project Location Details
Project Name Project Location Project District Project Tehsil Promoter Name
WAL STREET 88A Sector-88a, Village-harsaru, Gurugram GURUGRAM Harsaru ST Walton Builders LLP
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/934/666/2025/37 DATED 03.04.2025 RERA-GRG-1792-2024 05-Feb-2025 04-Feb-2025 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Yes 21-Feb-2025 By hand Deficiency notice
First hearing on 24.02.2025 View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/934/666/2025/37 DATED 03.04.2025 07-Apr-2025 RC Uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
24-Mar-2025 Ms. Prachi Singh, Planning Executive briefed about the facts of the project. Sh. Pawan Kumar (AR), Sh. Praveen Kumar (AR) are present on behalf of the promoter. Approved as proposed. The RC shall be issued after the above compliances including the submission of the road access permission within 3 months and correction of DPI, REP-I (A to H) and CA certificate for REP-1.  APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS View Order
10-Mar-2025 Ms. Prachi Singh, Planning Executive briefed about the facts of the project. Sh. Pawan Kumar (AR), Sh. Praveen Kumar (AR) are present on behalf of the promoter and states that reply to the remaining deficiencies has been submitted on 07.03.2025 which be examined by the office. The office also to visit the site to ascertain the accessibility and requirement of access permission. The director of the company to be present on the next date of hearing. The matter to come up on 24.03.2025. ADJOURNMENT View Order
24-Feb-2025 The matter is adjourned and to come up on 10.03.2025. EXAMINATION BY AUTHORITY ---