| 11-Feb-2025 |
Ms. Prachi Singh, Planning
Executive briefed about the facts of the project.
Sh. S.K. Kaushik (AR), Sh.
M.K. Tripathi (AR) and Sh. Aryan Bhatnagar (AR) are present on behalf of the
promoter who is a BIP holder for phase-I and Phase-II. Further, the license
renewal has been applied to DTCP and the said license is not part of Phase-II
which has been applied for extension under section 6 of the Act, 2016. The OC
in respect of the tower is also applied and revalidation fee deposited in
respect of the building plan shall be charged at the time of OC.
Approved as proposed subject
to corrections in REP-V and DPI. |
EXTENSION APPROVED |
View Order |
| 10-Feb-2025 |
The matter is adjourned and to come up on 11.02.2025 at 03:00 PM. |
ADJOURNMENT |
View Order |
| 27-Jan-2025 |
Ms. Prachi Singh, Planning
Executive briefed about the facts of the project.
Sh. S.K. Kaushik (AR) and Sh. Aryan
Bhatnagar (AR) are present on behalf of the promoter.
The concerned project executive to
inspect the site and report within ten days. Further, the promoter to submit
renewed building plan for Tower D and E and Commercial component.
The matter to come up on
10.02.2025. |
ADJOURNMENT |
View Order |
| 30-Dec-2024 |
The matter is adjourned and to come up on 27.01.2025. |
ADJOURNMENT |
View Order |
| 09-Dec-2024 |
The matter is adjourned and to come up on 30.12.2024. |
ADJOURNMENT |
View Order |
| 25-Nov-2024 |
The matter is adjourned and to come up on 09.12.2024. |
EXAMINATION BY AUTHORITY |
View Order |