10-Mar-2025 |
Ms. Nikita Mittal, Planning
Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of
the case.
Sh. Vineet Maheshwari (President), Sh. Siddhartha
Kapoor (AVP), Sh. Vedant Batra (AR) and Ms. Nisha Khanna (Architect) are
present on behalf of the promoter.
Approved as proposed subject to rectification of the
remaining minor deficiencies. Further, the promoter is directed to submit the
contact details of 43 more allottees for random verification of the consents
given by them. This is without prejudice to the rights of rest of the allottees
under section 14(2).
The registration certificate shall be issued after compliance of the
balance deficiencies along with the verification of the additional 43 consents. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
--- |
24-Feb-2025 |
Ms.
Nikita Mittal, Planning Executive and Ms. Asha, Chartered Accountant briefed
about the facts of the case.
Sh.
Vineet Maheshwari (President), Sh. Siddhartha Kapoor (AVP), Sh. Anisha (DM),
Sh. Vedant Batra (CS) are present on behalf of the promoter.
The
contact details of the allottees who have consented for change be submitted and
the office to ascertain the same at random. Further, a public notice to be
published of two weeks in three prominent newspapers, one Hindi and two English
newspapers intimating the revisions in existing layout plan for inviting
objections if any. Other deficiencies be also rectified by the applicant
promoter in meanwhile.
The
matter to come up on 10.03.2025. |
ADJOURNMENT |
--- |
27-Jan-2025 |
The matter is adjourned and to come up on 24.02.2025. |
ADJOURNMENT |
--- |
06-Jan-2025 |
Due to gazetted holiday, the matter is adjourned and to come up on 27.01.2025. |
ADJOURNMENT |
--- |
23-Dec-2024 |
The matter is adjourned and to come up on 06.01.2025. |
EXAMINATION BY AUTHORITY |
--- |