Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
Not Yet Approved/Certificate Not Uploaded Yet RERA-GRG-1777-2024 06-Nov-2024 06-Nov-2024 APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS NOT REQUIRED Not Yet -- First hearing View Form(A-H)
Project Listing Details
Date of Hearing Proceedings of the day Status Order
24-Mar-2025 Ms. Nikita Mittal, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the case. Sh. Vijay K. Goel (Partner) and Sh. Om Singh (AR) are present on behalf of the promoter. Approved as proposed subject to above corrections and submission of BG/DD of Rs. 25 lakhs for obtaining approved SPE and revised fire scheme approval within four months. This is without prejudice to the rights of the allottees under section 14 who have not consented for revision in building plans.   The amendment in registration certificate shall be issued after compliance of the balance deficiencies. APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS View Order
10-Mar-2025 The matter is adjourned and to come up on 24.03.2025. ADJOURNMENT ---
24-Feb-2025 Ms. Nikita Mittal, Planning Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the facts of the case. Sh. Vijay K Goel, Sh. Anil Kumar (AR) and Sh. Om Singh (AR) are present on behalf of the promoter. The contact details of the allottees who have consented for change be verified by the office at random. The promoter is directed to submit an unconditional bank undertaking with respect to the project. Further, a 2 week public notice to be published in three prominent newspapers (one Hindi and two English) intimating the revisions in building plan and for inviting objections, if any. Other deficiencies be also rectified by the applicant promoter in meanwhile. The matter to come up on 10.03.2025. ADJOURNMENT ---
27-Jan-2025 The matter is adjourned and to come up on 24.02.2025.  ADJOURNMENT ---
30-Dec-2024 The matter is adjourned and to come up on 27.01.2025.  ADJOURNMENT ---
16-Dec-2024 The matter is adjourned and to come up on 30.12.2024.  ADJOURNMENT ---
02-Dec-2024 The matter is adjourned and to come up on 16.12.2024. EXAMINATION BY AUTHORITY ---