18-Nov-2024 |
Sh.
Ashish Kush, Planning Executive briefed about the facts of the case.
Sh.
Purushottam Grover (AR), Ms. Priyanka Miglani (AR) and Sh. Anitesh Singh (AR)
are present on behalf of the promoter.
The
AR of the promoter stated that all the approvals are in place except Fire
Scheme Approval and Approved Service plan & estimates for which they will
submit the BG/DD of Rs 25 lakhs each as a security amount for submission of
same within 4 months. Further, states that the remaining deficiencies including
deficit fee will be submitted within two days and requested to grant the
registration certificate.
Keeping
in view of the above, the Authority decides to approve the project in principle
subject to the condition that the promoter shall submit the NOC for water
supply and storm water from the competent Authority for the Group
Housing/Convenient Shopping within a period of two months from the date of
grant of registration certificate. The promoter shall deposit the BG/DD
amounting to Rs. 25 lakhs each as security amount for submission of Fire Scheme
approval and Approved Service Plans and Estimates for the project within a
period of four months from the date of grant of registration certificate.
The
Registration Certificate shall be issued after submission of deficit fee and
rectification of remaining deficiencies including correction in A-H form and
Online DPI alongwith the revision in the timelines proposed for obtaining the
occupation certificate. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |