| Project Name | Project Location | Project District | Project Tehsil | Promoter Name |
|---|---|---|---|---|
| GOKULAM | SECTOR 7 , SOHNA | GURUGRAM | NB Buildcon Pvt. Ltd. |
| Project Id | Receiving Date | Online Submission Date | Current Status | Next Date of Hearing | Notice Dispatched | Notice Dispatched On | Notice Tracking Id | Notice Dispatched Remarks | View Notice | Initially Scrutinized Remarks |
|---|---|---|---|---|---|---|---|---|---|---|
| RERA-GRG-1733-2024 | 03-Sep-2024 | 03-Sep-2024 | EXTENSION APPROVED | NOT REQUIRED | Not Yet | -- | First hearing |
| Date of Hearing | Proceedings of the day | Status | Order |
|---|---|---|---|
| 14-Oct-2024 | Sh. Shashank Sharma, Associate Engineer Executive briefed about the facts of the project. Sh. Sunil Mehta (AR) is present on behalf of the promoter. Approved as proposed subject to rectification/compliances as indicated above at point no 26 and submission of annual audited report u/s 4(2)(l)(D) for the year 2023-24. The registration certification shall be issued subject to the submission of the above compliances. | EXTENSION APPROVED | View Order |
| 30-Sep-2024 | Sh. Shashank Sharma, Associate Engineer Executive briefed about the facts of the project. Sh. Sunil Mehta (AR) is present on behalf of the promoter. The Authority directs the STP along with concerned AEE to visit the site and check the status of construction at the site. Further, the promoter is directed to remove the remaining deficiencies pointed out above. The matter to come up on 14.10.2024. | EXAMINATION BY AUTHORITY | View Order |