16-Sep-2024 |
Sh.
Shashank Sharma, Associate
Engineer Executive and Sh. Ashish Dubey, Chartered Accountant briefed about the
facts of the case.
Sh. Ravi Aggarwal (Director),
Sh. Sanjay Kumar Varshney (ED), Siddhartha Kapoor (AVP), Sh. Vedant Batra (CS)
and Sh. Naveen Kumar (Architect) are present on behalf of the promoter.
Sh. Ravi Aggarwal (Director)
states that the revenue sharing with the landowner collaborator is in ratio of
69:31 percent but the withdrawal shall be only in proportion to the land cost
from the 70% account and an affidavit to this effect is already submitted in
the Authority. The requisite access permission from NHAI has already been
obtained and the BG for approval of SPE has already been submitted to DTCP and
the approved SPE shall be submitted within two months. The environment clearance is also applied,
and final approval will be submitted within four months and online transaction
of Rs. 25 lakhs have already been made to the Authority as a security amount
and assurance for its submission within stipulated time, failing which it shall
be forfeited. All the services shall be provided and maintained by the promoter
until their provisioning by public authorities and a declaration to this effect
shall be published in the brochure.
Approved as above. The RC shall be issued after rectification of
minor deficiencies in form A to H and DPI. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |