| 16-Dec-2024 |
Ms.
Prachi Singh, Planning Executive briefed about the facts of the project.
Sh.
Ranjit Bhambhu (AR) and Ms. Anupam Kohli (AR) are present on behalf of the
promoter.
The
promoter has clarified the total cost of the project along with the details of
expenditure incurred and expenditure to be incurred.
Further,
the AR of the promoter states that more than 80% of the work has been
completed.
Approved
as proposed subject to correction in REP- V and DPI. The extension certificate
shall be issued after the compliance of above. |
EXTENSION APPROVED |
View Order |
| 09-Dec-2024 |
Ms.
Prachi Singh, Planning Executive briefed about the facts of the project.
Sh.
Ranjit Bhambhu (AR), Sh. Vikas Singh (AR) and Ms. Anupam (AR) are present on
behalf of the promoter. The AR is submitting the deficit documents today along
with the details of expenditure already made and the expenditure remain to be
done.
The
matter to come up on 16.12.2024. |
ADJOURNMENT |
View Order |
| 28-Oct-2024 |
The matter is adjourned and to come up on 09.12.2024. |
ADJOURNMENT |
--- |
| 07-Oct-2024 |
The matter is adjourned and to come up on 28.10.2024. |
ADJOURNMENT |
--- |
| 09-Sep-2024 |
The matter is adjourned and to come up on 07.10.2024. |
ADJOURNMENT |
--- |
| 23-Aug-2024 |
The matter is adjourned and to come up on 09.09.2024. |
EXAMINATION BY AUTHORITY |
--- |