09-Sep-2024 |
Sh.
Shashank Sharma, Associate Engineer Executive and Sh. Ashish Dubey, Chartered
Accountant briefed about the facts of the case.
Sh.
Siddhartha Kapoor (AVP), Sh. Vedant Batra (CS) and Sh. Naveen (Architect) are
present on behalf of the promoter.
The AR of the promoter states that they have
submitted the NEFT of Rs 25 lakhs each vide NEFT no YESBR12024090500010827
dated 05.09.2024 and YESBR12024090500010828 dated 05.09.2024 as a security
amount for approval of Environmental Clearance and approved fire clearance within
3 months of the issuance of registration certificate. Further, the requisite BG
has been submitted to DTCP for final approval of service plans and estimates
and mining permission will be submitted before start of excavation at site.
Approved
as proposed subject to submission of approved fire clearance and EC within 3
months and approved SPE within two months from the grant of registration
certificate. The mining permission shall be obtained
before start of excavation at site.
The
RC shall be issued after rectification of other minor deficiencies in form A to
H and DPI and any other documents. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |